Texas Administrative Code
Title 16 - ECONOMIC REGULATION
Part 2 - PUBLIC UTILITY COMMISSION OF TEXAS
Chapter 24 - SUBSTANTIVE RULES APPLICABLE TO WATER AND SEWER SERVICE PROVIDERS
Subchapter H - CERTIFICATES OF CONVENIENCE AND NECESSITY
Section 24.239 - Sale, Transfer, Merger, Consolidation, Acquisition, Lease, or Rental
Current through Reg. 50, No. 13; March 28, 2025
(a) Application. A water supply or sewer service corporation or a water and sewer utility owned by an entity required to possess a certificate of convenience and necessity (CCN) must comply with this section. A municipality, district, or political subdivision may, but is not required to, comply with this section.
(b) Notice and filing requirements for approval of transaction. No later than 120 days before the effective date of any sale, transfer, merger, consolidation, acquisition, lease, or rental, an applicant must file an application with the commission and give public notice of the transaction in accordance with this section. Notice is considered given under this subsection on the later of:
(c) Transaction involving a municipal utility system. A transaction involving the sale of a municipal utility system to an entity to which this section applies must comply with this subsection. For purposes of this subsection, a municipal utility system means one or more retail water or sewer utility systems that comprise all or part of the facilities used by a municipally owned utility to provide retail water or sewer utility service. If the municipal utility system being acquired does not include all of the facilities used by the municipally owned utility to provide retail water or sewer utility service, the applicant must provide sufficient detail in its application to identify the specific retail water or utility systems and facilities being acquired.
(d) Intervention period. The intervention period for an application filed under this section must not be less than 30 days. The presiding officer may order a shorter intervention period for good cause shown.
(e) Notice.
(f) If the transferee cannot demonstrate adequate financial capability, the commission may require that the transferee provide financial assurance to ensure continuous and adequate retail water or sewer utility service is provided to both the requested area and any area already being served under the transferee's existing CCN. The commission will set the amount of financial assurance. The form of the financial assurance must meet the requirements of § 24.11 of this title (relating to Financial Assurance). The obligation to obtain financial assurance under this title does not relieve an applicant from any requirements to obtain financial assurance to satisfy another state agency's rules.
(g) The commission will, with or without a public hearing, investigate the sale, transfer, merger, consolidation, acquisition, lease, or rental to determine whether the transaction will serve the public interest. If the commission decides to hold a hearing, or if the transferee fails either to file the application as required or to provide public notice, the transaction proposed in the application may not be completed unless the commission determines that the proposed transaction serves the public interest.
(h) Before the expiration of the 120-day period described in subsection (a) of this section, the commission will determine whether to require a public hearing to determine if the transaction will serve the public interest. The commission will notify the transferee, the transferor, all intervenors, and the Office of Public Utility Counsel whether a hearing will be held. The commission may require a hearing if:
(i) If the commission does not require a public hearing, the sale, transfer, merger, consolidation, acquisition, lease, or rental may be completed as proposed:
(j) Within 30 days of the commission order that approves the sale, transfer, merger, consolidation, acquisition, lease, or rental to proceed as proposed, the transferee must provide a written update on the status of the transaction, and every 30 days thereafter, until the transaction is complete. The transferee must inform the commission of any material changes in its financial, managerial, and technical capability to provide continuous and adequate service to the requested area and the transferee's service area.
(k) If there are outstanding customer deposits, within 30 days of the actual effective date of the transaction, the transferor and the transferee must file with the commission, the following information supported by a notarized affidavit:
(l) Within 30 days after the actual effective date of the transaction, the transferee and the transferor must file a signed contract, bill of sale, or other appropriate documents as evidence that the transaction has closed as proposed. The signed contract, bill of sale, or other documents, must be signed by both the transferor and the transferee. If there were outstanding customer deposits, the transferor and the transferee must also file documentation that customer deposits have been transferred or refunded to the customers with interest as required by this section.
(m) The commission's approval of a sale, transfer, merger, consolidation, acquisition, lease, or rental of any water or sewer system or retail public utility expires 180 days following the date of the commission order allowing the transaction to proceed. If the sale has not been completed within that 180-day time period, the approval is void, unless the commission in writing extends the time period.
(n) If the commission does not require a hearing, and the transaction is completed as proposed, the commission may issue an order approving the transaction.
(o) A sale, transfer, merger, consolidation, acquisition, lease, or rental of any water or sewer system or retail public utility required by law to possess a CCN, or transfer of customers or service area, owned by an entity required by law to possess a CCN that is not completed in accordance with the provisions of TWC §13.301 is void.
(p) The requirements of TWC §13.301 do not applyto:
(q) If a utility's facility or system is sold and the utility's facility or system was partially or wholly constructed with customer contributions in aid of construction derived from specific surcharges approved by the regulatory authority over and above revenues required for normal operating expenses and return, the utility may not sell or transfer any of its assets, its CCN, or a controlling interest in an incorporated utility, unless the utility provides a written disclosure relating to the contributions to both the transferee and the commission before the date of the sale or transfer. The disclosure must contain, at a minimum, the total dollar amount of the contributions and a statement that the contributed property or capital may not be included in invested capital or allowed depreciation expense by the regulatory authority in rate-making proceedings. This subsection does not apply to a utility facility or system sold as part of a transaction where the transferor and transferee elected to use the fair market valuation process set forth in § 24.238 of this title (relating to Fair Market Valuation).
(r) For any transaction subject to this section, the retail public utility that proposes to sell, transfer, merge, acquire, lease, rent, or consolidate its facilities, customers, service area, or controlling interest must provide the other party to the transaction a copy of this section before signing an agreement to sell, transfer, merge, acquire, lease, rent, or consolidate its facilities, customers, service area, or controlling interest.