Texas Administrative Code
Title 16 - ECONOMIC REGULATION
Part 1 - RAILROAD COMMISSION OF TEXAS
Chapter 12 - COAL MINING REGULATIONS
Subchapter R - TEXAS ABANDONED MINE LAND RECLAMATION PROGRAM
Section 12.816 - Liens
Current through Reg. 50, No. 13; March 28, 2025
(a) Not later than six months after the date any projects to reclaim privately owned land are completed, the Commission:
(b) The statement shall be a lien on the land second only to a property tax lien. The amount of the lien shall not exceed the amount determined by either of two appraisals, as provided under § 12.815 of this title (relating to Appraisals), to be the increase in the market value of the land as a result of the restoration, reclamation, abatement, control, or prevention of the adverse effects of past mining practices.
(c) A lien shall not be filed under this section against the property of a person who did not consent to, participate in, or exercise control over the mining operation that necessitated the reclamation performed under this chapter.
(d) Not later than the 60th day after the date the lien is filed, an affected landowner may petition the Commission for a hearing on the amount of the lien. The hearing and any appeal shall be conducted pursuant to Chapter 2001, Government Code.
(e) The Commission may waive the lien if: