(a) Issuance of permit. The commission shall review the permit application submitted pursuant to § 26.20 of this title (relating to Application for Historic Buildings and Structures Permits) and may issue the permit, issue the permit with special conditions, request additional information for review, request a revised scope of work, or deny the permit application.
(b) Terms and conditions. When a permit is issued, it will contain all standard and special terms and conditions governing the project work.
(c) Permit period. No permit will be issued for less than six months, nor more than ten years, but may be issued for any length of time within those limits as deemed necessary by the commission in consultation with the applicant and project architect.
(d) Transferal of permits. No permit issued by the commission will be assigned by the permittee in whole or in part to any other institution, museum, corporation, organization, or individual without the consent of the commission.
(e) Permit expiration. The expiration date is specified in each permit and is the date by which all project work must be complete, including submission of the required completion report and fulfillment of all terms and conditions of the permit. It is the responsibility of the permittee, project architect, and professional firm to meet any and all permit terms and conditions prior to the expiration date listed on the permit.
(f) Expiration responsibilities. Professional firms must ensure that a project architect is assigned to a permit at all times, until all obligations under the permit have been fulfilled, regardless of whether the permit is active or has expired. Expired permits are considered to be in default and will be reported to the Antiquities Advisory Board. Commission staff or the board may request that the permittee, project architect, and/or professional firm appear and give an oral presentation regarding the need for an extension pursuant to subsection (e)(2) of this section, or the board may pursue other remedies as allowed under § 26.24 of this title (relating to Compliance with Rules for Historic Buildings and Structures Permits).
(g) Permit amendments. Proposed changes in the terms and conditions of the permit must be approved by the commission's executive director, the director of the DoA, or their designated representative. This includes changes in the permitted project plans and specifications that could affect the integrity of the structure, building, or site.
(h) Permit hold or cancellation. The commission may place on hold or cancel a Historic Buildings and Structures Permit pursuant to § 26.24 of this title under the following circumstances:
(i) Institutions of higher education. If an institution of higher education notifies the commission that it protests the terms of a permit granted to an institution of higher education under this section, the matter becomes a contested case under the provisions of the Administrative Procedure Act, Texas Government Code § 2001.051, et seq. The institution of higher education must notify the commission of its protest within 30 days of its receipt of notice of the terms of the permit to initiate a contested case. The hearing officer and the commission will follow the procedures and take into account the criteria listed in Texas Natural Resources Code, § 191.021 (c). Weighing these criteria against the criteria specified in § 26.20(b) of this title (relating to Standards for the Treatment of Historic Properties), the commission shall include a requirement in a permit only if the record before the committee establishes by clear and convincing evidence that such inclusion would be in the public interest.