Texas Administrative Code
Title 10 - COMMUNITY DEVELOPMENT
Part 1 - TEXAS DEPARTMENT OF HOUSING AND COMMUNITY AFFAIRS
Chapter 1 - ADMINISTRATION
Subchapter A - GENERAL POLICIES AND PROCEDURES
Section 1.4 - Protest Procedures for Contractors
Current through Reg. 49, No. 38; September 20, 2024
(a) Purpose. The purpose of this rule provides for the Department's compliance with 34 TAC Chapter 20, Subchapter F, Division 3, the rules of the Texas Comptroller of Public Accounts addressing procurement, which require state agencies to adopt protest procedures consistent with the Comptroller's procedures.
(b) Definitions. The following words and terms, when used in this subchapter, shall have the following meanings, unless the context clearly indicates otherwise.
(c) These procedures are for Department procurements only. Any actual or prospective bidder, offeror, or contractor who is aggrieved in connection with a solicitation, evaluation, or award may formally protest to the Department's Purchasing Officer.
(d) To be considered timely, the Protest must be filed in accordance with the requirements of 34 TAC § RSA 20.535(b).
(e) To be considered complete, the Protest must be in writing, signed by an authorized representative, notarized, and contain:
(f) The Purchasing Officer shall have the initial authority to settle and resolve the Dispute concerning the solicitation or award of a contract. The Purchasing Officer may dismiss the Protest if it is not timely filed or does not meet the requirements of this section. The Purchasing Officer may solicit written responses to the Protest from other Interested Parties.
(g) If the Protest is not resolved by mutual agreement, the Purchasing Officer will provide a written recommendation to the Department's Executive Director.
(h) The Executive Director shall issue a final written determination on the Protest within 15 calendar days after receipt of the Purchasing Officer's recommendation in accordance with the requirements of 34 TAC § RSA 20.537(c).
(i) In the alternative, the Executive Director may, in his or her discretion, refer the matter to the Department's Governing Board for their consideration at a regularly scheduled meeting. The decision of the Board shall be final.
(j) A protesting party may appeal the determination of the Executive Director under subsection (g) of this section to the Department's Governing Board. An appeal of the Executive Director's determination must be in writing and received by the Purchasing Officer not later than 10 calendar days after the date the Executive Director sent written notice of their determination. The scope of the appeal shall be limited to review of the Executive Director's determination. The protesting party must mail or deliver to all other interested parties a copy of the appeal, which must contain a certified statement that such copies have been provided.
(k) All documents collected by the Department as part of a solicitation, evaluation, and/or award of a contract shall be retained with the procurement file according to Department's Records Retention Schedule.
(l) The Department reserves all of its rights under 34 TAC § RSA 20.536. The Department may award a solicitation or award without delay, in spite of a timely filed Protest, to protect the best interests of the state.