Rules & Regulations of the State of Tennessee
Title 1220 - Tennessee Public Utility Commission
Subtitle 1220-04 - Division of Public Utilities
Chapter 1220-04-07 - Purchased Gas Adjustment Rules
Section 1220-04-07-.02 - GENERAL PROVISIONS
Current through September 24, 2024
(1) These Purchased Gas Adjustment (PGA) Rules are intended to permit the company to recover, in timely fashion, the total cost of gas purchased for delivery to its customers and to assure that the Company does not over-collect or under-collect Gas Costs from its customers.
(2) These Rules are intended to apply to all Gas Costs incurred in connection with the purchase, transportation and/or storage of gas purchased for general system supply, including, but not limited to, natural gas purchased from interstate pipeline transmission companies, producers, brokers, marketers, associations, intrastate pipeline transmission companies, joint ventures, providers of liquefied natural gas (LNG), liquefied petroleum gas (LPG), substitute, supplemental or synthetic natural gas (SNG), and other hydrocarbons used as feed-stock, other distribution companies and end-users, whether or not the Gas Costs are regulated by the Federal Energy Regulatory Commission and whether or not the provider of the gas, transportation or storage is affiliated with the Company.
(3) To the extent, practicable, any revision in the PGA shall be filed with the Authority no less than thirty (30) days in advance of the proposed effective date and shall be accompanied by the computations and information required by these Rules. It is recognized, however, that in many instances the Company receives less than thirty (30) days notice from its suppliers and that other conditions may exist which prevent the Company from providing thirty (30) days advance notice. Therefore, should circumstances occur where information necessary for the determination of an adjustment under these Rules is not available to the Company so that the thirty (30) days requirement can be met, the Authority may permit the Company to place rates into effect with shorter advance notice, upon good cause shown.
(4) The rates for gas service set forth in all of the Rate Schedules of the Company shall be adjusted pursuant to the terms of the PGA, or any specified portion of the PGA as determined by individual Rate Schedule(s).
(5) No provisions of these rules shall supersede any provision of a special contract approved by the Authority.
Authority: T.C.A. §§ 65 -2-102 and 65-4-104.