(1) Instrument transformers shall be tested:
(a) Prior to
initial installation.
(b) Upon
complaint.
(c) Whenever an approved
check, such as the variable burden method in the case of current transformers,
made whenever the meter is tested, indicates that a quantitative test is
required if the transformer will remain in service.
Authority: T.C.A. § 65-2-102.
Disclaimer: These regulations may not be the most recent version. Tennessee may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.