Rules & Regulations of the State of Tennessee
Title 0400 - Environment and Conservation
Subtitle 0400-40 - Water Resources (WPC)
Chapter 0400-40-14 - Pretreatment Requirements
Section 0400-40-14-.16 - UPSET PROVISION

Current through September 24, 2024

(1) Definition.

For the purposes of this chapter, "Upset" means an exceptional incident in which there is unintentional and temporary noncompliance with categorical Pretreatment Standards because of factors beyond the reasonable control of the Industrial User. An Upset does not include noncompliance to the extent caused by operational error, improperly designed treatment facilities, inadequate treatment facilities, lack of preventive maintenance, or careless or improper operation.

(2) Effect of an upset.

An Upset shall constitute an affirmative defense to an action brought for noncompliance with categorical Pretreatment Standards if the requirements of paragraph (3) of this rule are met.

(3) Conditions necessary for a demonstration of upset.

An Industrial User who wishes to establish the affirmative defense of Upset shall demonstrate, through properly signed, contemporaneous operating logs, or other relevant evidence that:

(a) An Upset occurred and the Industrial User can identify the cause(s) of the Upset;

(b) The facility was at the time being operated in a prudent and workman-like manner and in compliance with applicable operation and maintenance procedures;

(c) The Industrial User has submitted the following information to the WWF and Control Authority within 24 hours of becoming aware of the Upset (if this information is provided orally, a written submission must be provided within five days):
1. A description of the Indirect discharge and cause of noncompliance;

2. The period of noncompliance, including exact dates and times or, if not corrected, the anticipated time the noncompliance is expected to continue;

3. Steps being taken and/or planned to reduce, eliminate and prevent recurrence of the noncompliance.

(4) Burden of proof.

In any enforcement proceeding the Industrial User seeking to establish the occurrence of an Upset shall have the burden of proof.

(5) Reviewability of agency consideration of claims of upset.

In the usual exercise of prosecutorial discretion, Agency enforcement personnel should review any claims that non-compliance was caused by an Upset. No determinations made in the course of the review constitute final Agency action subject to judicial review. Industrial Users will have the opportunity for a judicial determination on any claim of Upset only in an enforcement action brought for noncompliance with categorical Pretreatment Standards.

(6) User responsibility in case of upset.

The Industrial User shall control production of all discharges to the extent necessary to maintain compliance with categorical Pretreatment Standards upon reduction, loss, or failure of its treatment facility until the facility is restored or an alternative method of treatment is provided. This requirement applies in the situation where, among other things, the primary source of power of the treatment facility is reduced, lost or fails.

Authority: T.C.A. §§ 69-3-101 et seq. and 4-5-201 et seq.

Disclaimer: These regulations may not be the most recent version. Tennessee may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.