Section 0400-15-01-.12 - FINAL OPERATION AND MAINTENANCE PLAN
Current through September 24, 2024
(1) Purpose
The purpose of the O & M process is to provide funds and activities that will ensure the long term treatment and/or maintenance of a site that is required based on the Remedial Investigation /Feasibility Study and the Remedial Action.
(2) Description of O & M Activities
A plan shall be submitted by the responsible party which details the activities that will occur during the operation and maintenance period. A reporting schedule and review cycle shall be established. The reporting schedule shall detail the reporting requirements for the proposed activities and the review cycle will establish a review of the O & M process. Below are items that shall be included, as appropriate, in the plan. The plan and schedule shall be submitted to the Department for review and approval prior to the implementation:
(3) Financial assurance may be required by the Commissioner to insure the O & M costs. This financial assurance shall be provided in a form, amount, and in the manner approved by the Commissioner.
(4) Reporting
A reporting schedule and review cycle shall be established. The schedule shall detail the requirements for the proposed activities with associated costs. The schedule will establish a periodic review of the O & M.
(5) Petition to Discontinue Pump and Treat of Ground Water
The Department realizes that in some cases pump and treat methods of ground water remediation may fail to achieve ground water remediation goals established under Rule 0400-15-01-.08. Unless otherwise determined by the Department, the following shall apply:
Authority: T.C.A. §§ 68-212-201 et seq. and 4-5-201 et seq.