Rules & Regulations of the State of Tennessee
Title 0400 - Environment and Conservation
Subtitle 0400-11 - Division of Solid Waste Management (Solid Waste Program)
Chapter 0400-11-01 - Solid Waste Processing and Disposal
Section 0400-11-01-.07 - FEE SYSTEM FOR NON-HAZARDOUS DISPOSAL AND CERTAIN NON-HAZARDOUS PROCESSORS OF SOLID WASTE
Current through September 24, 2024
(1) General
(2) Application Filing/Processing Fees
1. Disposal Facility |
|
(i) Class I |
|
Hydrogeologic |
$ 4,000 |
Design and Construction Plans |
$ 6,000 |
(ii) Class II | |
Hydrogeologic |
$ 4,000 |
Design and Construction Plans |
$ 6,000 |
(iii) Class III |
$ 3,000 |
2. Processing Facility |
$ 1,000 |
3. Major Modifications |
$ 2,000 |
4. Special Waste Evaluation |
$ 300 |
5. Transfer Station |
$ 500 |
6. Transfer of Ownership |
$ 1,000 |
7. Special Waste Recertification |
$ 150 |
(3) Annual Maintenance Fees
1. Disposal Facilities |
|
(i) Class I (Tons/Year) |
|
(I) Greater than 50,000 |
$15,000 |
(II) 25,000 to 50,000 |
$10,000 |
(III) Less than 25,000 |
$ 5,000 |
(IV) Zero Tons (Post Closure Period) |
$ 1,000 |
(ii) Class II (Tons/Year) |
|
(I) Greater than 1,000 T |
$10,000 |
(II) Less than 1,000 T |
$ 4,000 |
(iii) Class III (Tons/Year) |
|
(I) Greater than 10,000 |
$ 4,000 |
(II) Less than 10,000 |
$ 3,000 |
(iv) Class IV (Tons/Year) |
|
(I) Greater than 10,000 |
$ 4,000 |
(II) Less than 10,000 |
$ 3,000 |
2. Processing Facilities |
$ 3,000 |
3. Transfer Station |
$ 1,500 |
4. Reserved. |
|
5. Land Application Facility |
$ 100 |
(4) Baled Waste Inspection Fee - Any facility that intends to receive baled waste that was not baled in accordance with a permit issued in accordance with the Solid Waste Management Act, shall pay a $3.00 per bale inspection fee prior to the receipt of the waste.
(5) Facility Inspection Fee - Any person who has a municipal solid waste disposal facility permit or incinerator permit that receives waste is assessed a facility inspection fee of $0.35 on each ton of municipal solid waste received. This fee shall be calculated in the same manner and paid at the same time as the surcharge in Rule 0400-11-01-.08.
(6) Schedule for timely action on permit applications:
1. Hydrogeologic Report for Disposal Facilities |
30 days |
2. Design and Construction Plans for Disposal & Compost Facilities |
45 days |
1. Disposal Facility |
|
(i) Class I |
270 days |
(ii) Class II |
270 days |
(iii) Class III |
240 days |
2. Processing Facility |
|
(i) Permit By Rule |
90 days |
(ii) Compost Facility |
120 days |
3. Major Modification |
|
(i) Regulatory Requirement |
180 days |
(ii) Application | |
(I) Plans Only |
240 days |
(II) Hydrogeologic |
270 days |
4. Minor Modifications |
|
(i) Engineering Review |
90 days |
(ii) Reserved. | |
5. Waste Evaluation |
30 days |
Authority: T.C.A. §§ 4-5-201, et seq.; 68-203-101, et seq.; 68-211-101, et seq.; and 68-211-801, et seq.