Current through Register Vol. 50, page 114, March 25, 2024

Except in the case of POTWs, calculation of any permit limits, standards, or prohibitions which are based on production or another measure of operation shall not be based on the design production capacity but on a reasonable measure of actual production of the facility. For new sources or new dischargers, actual production shall be estimated using projected production at the time period of the calculated permit limits.

General Authority: SDCL 34A-2-30.

Law Implemented: SDCL 34A-2-38, 34A-2-41.

Disclaimer: These regulations may not be the most recent version. South Dakota may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.