South Dakota Administrative Rules
Title 74 - Department of Environment And Natural Resources
Article 74:36 - Air pollution control program
Chapter 74:36:20 - Construction permits for new sources or modifications
Section 74:36:20:10 - Time period for department's recommendation

Universal Citation: SD Admin Rules 74:36:20:10
Current through Register Vol. 50, page 114, March 25, 2024

The department shall recommend issuance or denial of a construction permit within 180 days after the submission of a complete application and all other additional information necessary for the department to make an informed decision. A recommendation to issue a permit shall include a draft permit with appropriate conditions to ensure compliance with the act or the Clean Air Act. Failure of the department to act on an application entitles the applicant to petition for and obtain a contested case review of the application without waiting for a department recommendation. The petition must conform to the requirements of article 74:09.

General Authority: SDCL 34A-1-6, 34A-1-21.

Law Implemented: SDCL 34A-1-21.

Disclaimer: These regulations may not be the most recent version. South Dakota may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.