An application for a construction permit for a new source or modification must include the following information to be considered a complete application:
(1) The following general company information:
(2) A description of the plant and its processes and products;
(3) The following information on emissions:
(4) If available, a copy of any prepared plans and the specifications of any equipment or other facilities that may affect the source, including pollution control devices;
(5) A signed and notarized certification of applicant form;
(6) The results of any air dispersion modeling required by the department;
(7) The results of any stack performance testing required by the department; and
(8) Any other information requested by the department that is relevant to determining compliance with the act or the Clean Air Act.
The application must be signed by the responsible official or designated representative.
General Authority: SDCL 34A-1-6, 34A-1-21.