South Dakota Administrative Rules
Title 74 - Department of Environment And Natural Resources
Article 74:36 - Air pollution control program
Chapter 74:36:20 - Construction permits for new sources or modifications
Section 74:36:20:05.01 - Procedures for an insignificant increase in allowable emissions

Universal Citation: SD Admin Rules 74:36:20:05.01

Current through Register Vol. 50, page 114, March 25, 2024

The department shall take the following final action on the proposed insignificant increase in allowable emissions within 90 days after receipt of a complete application for an insignificant increase in allowable emissions:

(1) Issue the construction permit as proposed;

(2) Deny the application for a construction permit; or

(3) Determine the application should be processed as a construction permit following the procedural requirements in §§ 74:36:20:06 to 74:26:20:10, inclusive.

The secretary shall issue the construction permit for an insignificant increase in allowable emissions without the procedural requirements applicable to obtaining a construction permit.

General Authority: SDCL 34A-1-6, 34A-1-21.

Law Implemented: SDCL 34A-1-21.

Disclaimer: These regulations may not be the most recent version. South Dakota may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.