South Dakota Administrative Rules
Title 74 - Department of Environment And Natural Resources
Article 74:36 - Air pollution control program
Chapter 74:36:18 - Regulations for state facilities in the Rapid City area
Section 74:36:18:06 - Contents of permit
Current through Register Vol. 50, page 114, March 25, 2024
The construction activity and continuous operation activity permit shall include the following:
(1) The signature of either the secretary or the chairman;
(2) The name of the person, company, political subdivision, agency, or institution granted a permit;
(3) The type of operation;
(4) The mailing address;
(5) The date the permit was granted and on which it will expire;
(6) A permit number;
(7) The name of a designated person or officer responsible for the permitted activity;
(8) A statement granting a permit by the board or secretary and any conditions that the board or secretary may impose to ensure compliance with the Act;
(9) Emission limits and standards necessary to assure compliance with applicable requirements of the Clean Air Act;
(10) Record keeping and reporting requirements;
(11) A severability clause to ensure the continued validity of the various permit requirements if any portion of the permit are challenged; and
(12) Provisions stating the following:
General Authority: SDCL 34A-1-6, 34A-1-21.
Law Implemented: SDCL 34A-1-21.