Current through Register Vol. 50, page 114, March 25, 2024

The use of loose, baled, or processed waste tires for structural or construction purposes is allowed without obtaining a solid waste storage permit if:

(1) The construction project is completed within six months of receiving the first load of tires;

(2) Waste tires not used for the project are disposed of within 30 days of completion of the project and in a manner consistent with this chapter; and

(3) The use is stated in and is in accordance with § 74:27:22:04.

Any tire from a structure that becomes loose or no longer serves its original intended purpose is considered a waste tire and is subject to the requirements of this chapter. Baled tires are considered waste tires until they have been approved for use by the department according to this chapter.

General Authority: SDCL 34A-6-1.6, 34A-6-87.1.

Law Implemented: SDCL 34A-6-1.6, 34A-6-87.1.

Disclaimer: These regulations may not be the most recent version. South Dakota may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.