South Dakota Administrative Rules
Title 74 - Department of Environment And Natural Resources
Article 74:27 - Solid waste
Chapter 74:27:22 - Collection, transportation, storage, and processing of waste tires
Section 74:27:22:03 - Use of waste tires for structural or construction purposes
Current through Register Vol. 50, page 114, March 25, 2024
The use of loose, baled, or processed waste tires for structural or construction purposes is allowed without obtaining a solid waste storage permit if:
(1) The construction project is completed within six months of receiving the first load of tires;
(2) Waste tires not used for the project are disposed of within 30 days of completion of the project and in a manner consistent with this chapter; and
(3) The use is stated in and is in accordance with § 74:27:22:04.
Any tire from a structure that becomes loose or no longer serves its original intended purpose is considered a waste tire and is subject to the requirements of this chapter. Baled tires are considered waste tires until they have been approved for use by the department according to this chapter.
General Authority: SDCL 34A-6-1.6, 34A-6-87.1.
Law Implemented: SDCL 34A-6-1.6, 34A-6-87.1.