Section 74:05:08:13.02 - Facilities plan submittal

Universal Citation: SD Admin Rules 74:05:08:13.02

Current through Register Vol. 50, page 114, March 25, 2024

Any applicant requesting financial assistance for a wastewater treatment works or storm water project must prepare a facilities plan. A facilities plan is not required from an applicant requesting funding for other types of projects. The facilities plan shall at minimum provide the information contained in § 74:05:08:01(8). The applicant shall be notified of any deficiencies in the draft facilities plan submitted with the application. A completed facilities plan must be received by the department to initiate the environmental review process. The facilities plan is not considered complete until the following items are received:

(1) Information to address the deficiencies identified by the secretary;

(2) Receipt of evidence of advertisement of a public hearing;

(3) Minutes from the public hearing;

(4) Responses from the U.S. Fish and Wildlife Service; South Dakota Department of Game, Fish and Parks; Natural Resources Conservation Service; U.S. Army Corps of Engineers; and the State Historical Preservation Office; and

(5) Resolution of any issues identified in the public hearing or by the agencies listed in § 74:05:08:13.02(4).

General Authority: SDCL 46A-1-60.3.

Law Implemented: SDCL 46A-1-60.1 to 46A-1-60.3.

Disclaimer: These regulations may not be the most recent version. South Dakota may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.