Projects which are receiving state assistance must adhere to the following time limits. All times refer to days after the declaration of an emergency or disaster by the Governor.

Work

Initiation

Completion

Category

of Work

of Work

(1) Debris clearance

30 days

180 days

(2) Emergency measures

30 days

180 days

(3) Permanent work

18 months

The time limits imposed by §§ 50:02:01:15 and 50:02:01:16 and this section may be extended by the director of the Division of Emergency Management for up to six months if requested and justified in writing by the applicant. Justification must be based on extenuating circumstances beyond the control of the applicant.

General Authority: SDCL 33-15-24.8.

Law Implemented: SDCL 33-15-24.8.

Disclaimer: These regulations may not be the most recent version. South Dakota may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.