Projects which are receiving state assistance must adhere to the following time limits. All times refer to days after the declaration of an emergency or disaster by the Governor.
Work |
Initiation |
Completion |
Category |
of Work |
of Work |
(1) Debris clearance |
30 days |
180 days |
(2) Emergency measures |
30 days |
180 days |
(3) Permanent work |
18 months |
The time limits imposed by §§ 50:02:01:15 and 50:02:01:16 and this section may be extended by the director of the Division of Emergency Management for up to six months if requested and justified in writing by the applicant. Justification must be based on extenuating circumstances beyond the control of the applicant.
General Authority: SDCL 33-15-24.8.
Law Implemented: SDCL 33-15-24.8.
Disclaimer: These regulations may not be the most recent version. South Dakota may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.