South Dakota Administrative Rules
Title 31 - Governor's Office of Economic Development
Article 31:02 - Ethanol infrastructure incentive program
Chapter 31:02:01 - Ethanol Infrastructure Incentive Program
Section 31:02:01:09 - Remedies

Universal Citation: SD Admin Rules 31:02:01:09

Current through Register Vol. 51, page 43, September 23, 2024

If there is a default pursuant to the provisions of § 31:02:01:08, the grantee shall repay the grant to GOED within thirty days of a written demand from GOED. GOED may retain counsel and commence a civil action to recover any grant funds that a grantee is required to repay. GOED may forgive a default under this chapter if any of the following conditions are met:

(1) There are fuel shortages that make compliance impractical;

(2) There are changes in fuel market conditions that make compliance impractical;

(3) There are changes in state or federal regulations that make compliance impractical.

For any grant involving the installation of ethanol blender pumps and a default pursuant to the provisions of subdivision 31:02:01:08(4), the amount sought to be repaid may be prorated based upon the number of months less than twenty-four that ethanol blends were sold.

General Authority: SDCL 10-47B-164.1, 10-47B-164.2.

Law Implemented: SDCL 10-47B-164.1.

Disclaimer: These regulations may not be the most recent version. South Dakota may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.