Except for dairies with three-phase balanced primary service, each of the following five steps for the load box test is conducted for at least two minutes:

(1) Step One: The load box is de-energized, the dairy remains "on," and the data is recorded;

(2) Step Two: The load box is de-energized, the dairy shut "off," and the data is recorded;

(3) Step Three: The load box is set to half load, the dairy shut "off," and the data is recorded;

(4) Step Four: The load box is set to full load, the dairy shut "off," and the data is recorded; and

(5) Step Five: The load box is set to full load, the dairy is turned "on," and the data is recorded.

For dairies with three-phase balanced primary service, the service provider performs steps one and two.

General Authority: SDCL 49-47-2.

Law Implemented: SDCL 49-47-2, 49-47-3.

Disclaimer: These regulations may not be the most recent version. South Dakota may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.