Section 20:10:37:18 - Notice requirements for transmission line construction

Universal Citation: SD Admin Rules 20:10:37:18

Current through Register Vol. 50, page 114, March 25, 2024

Each transmission pipeline operator within the jurisdiction of the pipeline safety program shall, prior to the construction of a new transmission line, or a relocation or replacement of a transmission line as defined in the Code of Federal Regulations, Title 49, Part 192 as of July 1, 2021:

(1) Submit the information below to the commission's pipeline safety program no later than 60 days prior to the commencement of construction, relocation, or replacement:

(a) Pipeline operator's name and mailing address;

(b) Estimated dates construction is scheduled to begin and end;

(c) Map showing location and proposed route of pipeline;

(d) Identified gas transmission Integrity Management Program high consequence area, if applicable;

(e) Proposed steel pipeline specifications, including size, weight, grade, wall thickness, and coating;

(f) Proposed plastic pipe specifications, including size and Standard Dimension Ratio;

(g) Proposed design and maximum allowable operating pressure of pipeline;

(h) Pressure test procedures and method of pressure test prior to operations;

(i) Proposed type of cathodic protection;

(j) Minimum burial depths of pipeline at time of construction;

(k) Proposed location and type of pipeline safety equipment;

(l) Proposed type of highway and water crossing, such as whether it will be bored and cased, bored only, or trenched;

(m) Written construction procedures;

(n) Name of construction company if known at the time of filing the Notice; and

(o) Pipeline operator's contact name and phone number;

(2) In the event of an emergency, as defined in the pipeline operator's operations manual, give telephonic notice of emergency construction, relocation, or replacement to the commission's pipeline safety program;

(3) Significant construction modifications shall be submitted to the pipeline safety program; and

(4) Submit the information below to the commission's pipeline safety program no later than 60 days prior to the commencement of operation:

(a) Operation and maintenance manual;

(b) Emergency procedures;

(c) Anti-drug and alcohol plan;

(d) Public Awareness plan;

(e) Damage prevention program;

(f) Abnormal operations; and

(g) Operator's qualification plan.

General Authority: SDCL 49-34B-4, 49-34B-19.

Law Implemented: SDCL 49-34B-3, 49-34B-4, 49-34B-8, 49-34B-19, 49-34B-27.

Disclaimer: These regulations may not be the most recent version. South Dakota may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.