If the small generator facility's tier 2 application is not approved, the applicant may submit a new application, including the difference in the application fee or deposit, for consideration under tier 3 or tier 4 procedures without losing its original queue position. The new application must be submitted within 15 business days of notice that the application was not approved. If requested, the public utility shall provide a written explanation of why the application was not approved.

General Authority: SDCL 49-34A-27, 49-34A-93.

Law Implemented: SDCL 49-34A-27, 49-34A-93.

Disclaimer: These regulations may not be the most recent version. South Dakota may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.