South Dakota Administrative Rules
10:09 - HIGH PERFORMANCE BUILDING DESIGN AND CONSTRUCTION
Chapter 10:09:03 - Waivers.
10:09:03:02 - Procedures for granting waivers

10:09:03:02. Procedures for granting waivers. An agency may request a waiver by submitting a written request to the OSE prior to the construction documents phase of the project. OSE will provide a written response to the waiver request within 30 days of receipt. The written waiver request must include:

(1) Justification why a high performance building standard cannot be met; and

(2) Steps the owner will take to meet as many energy points as possible under the rating system; and

(3) If the request is based on the inability to recoup costs in 15 years, the calculations as defined in ยง 10:09:04:01; or

(4) If the square footage of the renovation project is less than fifty percent of the total square footage of the building being renovated, a three year building use plan.

Source: 34 SDR 323, effective July 3, 2008.

General Authority: SDCL 5-14-38.

Law Implemented: SDCL 5-14-38.

Disclaimer: These regulations may not be the most recent version. South Dakota may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.