10:09:02:01. State building project certifications. The following steps must be taken to certify a project as a high performance building:

(1) The OSE shall designate the high performance building standard to be used on the project;

(2) The owner shall submit the owner's project requirements to the OSE and A/E during the programming phase;

(3) The A/E, at the request of the OSE shall complete and present an approved high performance building standard checklist to the owner and OSE;

(4) The A/E shall submit the initial basis of design to the owner and OSE no later than the completion of the schematic design phase;

(5) The A/E shall submit an OSE approved energy model to the owner before completion of the design development phase verifying the required energy optimization performance credits are achievable;

(6) The owner, OSE, A/E, commissioning team, and building contractor shall complete all the procedural requirements designated in the standard in the time frame required;

(7) A copy of the original building certification document must be submitted to the OSE within 90 days of certification;

(8) OSE shall keep the building certification document on file for the lifetime of the building; and

(9) A copy of the building certificate may be kept on file by the owner.



Source: 34 SDR 323, effective July 3, 2008; 41 SDR 218, effective June 30, 2015.

General Authority: SDCL 5-14-38.

Law Implemented: SDCL 5-14-38.

Disclaimer: These regulations may not be the most recent version. South Dakota may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.