South Carolina Code of Regulations
Chapter 61 - DEPARTMENT OF HEALTH AND ENVIRONMENTAL CONTROL
Subchapter 61-86.1 - STANDARDS OF PERFORMANCE FOR ASBESTOS PROJECTS
Section 61-86.1.X - NESHAP PROJECTS

Universal Citation: SC Code Regs 61-86.1.X

Current through Register Vol. 48, No. 9, September 27, 2024

A. Applicability.

The notification/application, work practice, air sampling, clean-up and disposal requirements of this Section shall apply to each owner/operator of a renovation asbestos project, where the combined amount of RACM to be stripped, removed, dislodged, cut, drilled, or similarly disturbed includes at least 260 linear feet on pipes, or 160 square feet on other facility components, or 35 cubic feet off of facility components where the area or length could not be measured prior to abatement.

B. Notification/Application.

1. Each owner/operator of a renovation or demolition operation to which this Section applies shall:
a. Provide the Department with written notification/application at least ten complete working days prior to any renovation or demolition operation, and pay all applicable project fees. Acceptable delivery of the notification and fee payment is by U.S. Postal Service or commercial delivery service, by hand, or by other methods deemed acceptable by the Department.

b. Update/revise the notification/application and pay appropriate fees as required when any previously-notified information changes, including but not limited to, when the amount of asbestos affected increases or decreases more than five percent (5%), when the project start or completion date changes, when the disposal site changes, and/or the project has been cancelled. The owner/operator shall notify the Department by telephone and follow up in writing as soon as possible before, but not later than, the following working day.

c. Prior to each demolition operation, and upon request for renovations, provide the Department with a complete legible copy of the asbestos building inspection report.

d. Begin abatement on the start date contained in the Department-issued asbestos project license.

e. Project designs shall be submitted at the Department's request.

2. When the asbestos stripping or removal operation or demolition operation covered by this Section will begin on a date earlier than the previously-notified start date, the owner/operator shall provide the Department with written notification/application of the new start date at least ten working days before asbestos stripping or removal work will begin. The Department may waive this requirement on a case-by-case basis, although the owner/operator shall provide all required information in writing prior to commencing any abatement activities.

3. The owner/operator of an asbestos stripping or removal operation covered by this Section shall:
a. Notify the Department of the new start date by telephone as soon as possible before, but notlater than, the original start date, when the renovation will begin after the date contained in the initial notification/application and in the asbestos project license issued by the Department.

b. Provide the Department with an updated written notice of the new start date as soon as possible before, but not later than, the original start date. Acceptable delivery of the updated notice is by the U.S. Postal Service or commercial delivery service, by hand, or by other methods deemed acceptable by the Department.

c. Provide the Department with an updated written notice of the new completion date as soon as possible before, but not later than, one working day following the completion of the project when the asbestos stripping or removal operation covered by this Section will end on a date earlier than contained in the initial notification and in the asbestos project license issued by the Department. Acceptable delivery of the updated notice is by the U.S. Postal Service or commercial delivery service, by hand, or by other methods deemed acceptable by the Department.

d. Provide the Department with written notification/application of the new completion date as soon as possible before, but not later than, the original completion date when the asbestos stripping or removal operation covered by this Section will end on a date later than contained in the initial notification/application and in the asbestos project license issued by the Department. Acceptable delivery of the updated notice is by the U.S. Postal Service or commercial delivery service, by hand, or by other methods deemed acceptable by the Department.

4. The written notification /application shall include:
a. Indication whether the notification/application is an original, revision, or cancellation;

b. Name, address, and telephone number of the owner/operator;

c. Type of operation: demolition or renovation;

d. Description of the facility or affected part of the facility, including the square footage, number of floors, age, and prior, present, and intended use of the facility;

e. Description of the procedures and analytical methods used to detect the presence of ACM (regulated and non-regulated), date of inspection, and name, address, telephone number, and license number of the building inspector;

f. An estimate of the approximate amount of RACM and Category II nonfriable ACM to be removed from the facility in terms of length of pipe in linear feet; surface area in square feet on other facility components, or volume in cubic feet, if already off facility components;

g. Location and street address (including building number or name and floor or room number, if appropriate), city, county, and state of the facility being demolished or renovated;

h. Scheduled starting and completion dates of asbestos renovation or demolition;

i. Description of planned renovation or demolition work to be performed, emission control measure(s) to be employed, and a description of the affected facility or facility components;

j. Description of the engineering controls and procedures to be used to comply with the work practice requirements of this regulation;

k. Name and location of the waste disposal site where the regulated asbestos-containing waste material will be deposited. Regulated asbestos-containing waste must be deposited into a landfill approved or permitted to accept asbestos waste;

l. Description of procedures to be followed in the event that unexpected RACM is found or Category I or II nonfriable ACM becomes regulated;

m. Name, address, and telephone number of the waste transporter; and

n. Printed name and signature of the asbestos owner/operator submitting the notification, and date signed.

5. A complete notification/application shall contain all of the above information and shall be reported on a form similar to the one found in 40 CFR Part 61, Subpart M, as amended, and any subsequent amendments and editions.

C. Work Practice Requirements.

1. Preparation.
a. Prior to beginning removal, each owner/operator engaged in a renovation project subject to this Section shall:
(1) Define the work area using barrier tape and danger signs in accordance with the following or OSHA 29 CFR 1926.1101, as amended, and any subsequent amendments and editions, if more stringent:
(a) Warning signs and tape that clearly separate the regulated area shall be provided and displayed at each location where a regulated area is required to be established by this Section. Signs shall be posted at a distance from the regulated area such that an employee may read the signs and take necessary protective steps before entering the area marked by the signs.

(b) The warning signs required by this Section shall bear the following information:

DANGER

ASBESTOS

CANCER AND LUNG DISEASE HAZARD

AUTHORIZED PERSONNEL ONLY

(2) Shut down, lock, and tag out all HVAC equipment in or passing through the work area. Seal each intake and exhaust opening and any seam in system components with two sheets of 6-mil polyethylene sheeting and tape.

(3) Detach and wet clean removable electrical, heating, and ventilating equipment and other items which may be connected to asbestos surfaces.

(4) Remove existing filters from the HVAC system and dispose of as asbestos-contaminated waste.

(5) Seal each opening between the work area and uncontaminated areas including windows, doorways, elevator openings, corridor entrances, drains, ducts, electrical outlets, grills, grates, diffusers, and skylights with a critical barrier consisting of at least two independent sheets of 6-mil or thicker polyethylene sheeting secured in place. These critical barriers must be maintained leak-tight for the duration of asbestos abatement.

(6) Thoroughly clean and remove all movable objects from the work area.

(7) Thoroughly clean, then cover and secure each non-movable object in the work area with at least one sheet of 4-mil or thicker polyethylene sheeting.

(8) Use polyethylene sheeting to isolate contaminated from uncontaminated areas, and ensure the sheeting is attached securely in place and properly maintained at all times.

(9) Prevent contamination of carpet with ACM, or dispose of the carpet as asbestos-contaminated waste.

(10) Cover floors not being abated with at least two layers of 6-mil or thicker polyethylene sheeting. Floor sheeting shall be installed first and shall extend at least 12 inches up the walls and be taped into place. No seams shall be located at wall/floor joints. Spray-applied polyethylene coating shall not be used.

(11) Cover walls and ceilings not being abated with at least one sheet of 4-mil or thicker polyethylene sheeting. Wall sheeting shall be installed to minimize joints and shall extend at least six inches beyond wall/floor joint and be taped into place. Ceiling sheeting shall extend at least 12 inches down the wall and be sized and taped into place. No seams shall be located at wall/ceiling or wall/wall joints.

(12) Construct a decontamination enclosure system adjoining the contained work area. The decontamination enclosure shall be built in a manner that will prevent track-out of RACM, and shall consist of: a clean room equipped with appropriate storage containers and adequate space for changing clothing; an air lock; a shower room containing hot and cold or warm running water controllable at the tap; and an equipment room suitable for storage of tools and equipment.

(13) Construct a clear viewing port measuring at least 24 inches by 24 inches in an external wall of the contained work area to allow unobstructed observation of abatement activities in the work area.

(14) Operate negative pressure differential equipment with HEPA filtration continuously from the time that barrier construction is completed through the time that acceptable final clearance air monitoring results are obtained.

(15) Utilize a manometer to measure negative pressure differential and operate it in accordance with the General Requirement Section of this regulation.

2. Removal.

Each owner/operator engaged in a renovation asbestos project subject to this Section shall ensure that:

a. Prior to removal, all RACM is thoroughly wet through to the substrate using amended water.

b. All RACM that has been stripped or removed in sections or units shall be:
(1) Thoroughly wet during stripping or removal and shall remain wet until disposed of in accordance with this regulation and 40 CFR 61.150, as amended, and any subsequent amendments and editions;

(2) Carefully lowered to the ground or floor, not dropped or thrown; and

(3) When removed or stripped at an elevation greater than 50 feet above ground level, transported to the ground via leak-tight chutes or containers.

c. At no time shall an owner/operator allow RACM to accumulate or become dry.

d. Structural components are thoroughly wet prior to wrapping in polyethylene sheeting for disposal.

e. For facility components such as reactor vessels, large tanks, and steam generators (but not beams, which must be stripped), ACM is not required to be stripped if the following requirements are met:
(1) The component is removed, transported, stored, disposed of, or reused without disturbing or damaging any of the ACM;

(2) The component is encased in leak-tight wrappings; and

(3) The leak-tight wrapping is labeled in accordance with EPA Regulation 40 CFR 61.149(d)(1)(i),(ii),and(iii), as amended, and any subsequent amendments and editions, during all loading, unloading, and storage operations.

f. When double polyethylene bags of at least 6-mil thickness are used for waste, bags shall be leak-tight. Excess air shall be removed from bags prior to sealing using a vacuum equipped with a HEPA filtration system in accordance with OSHA regulation 29 CFR 1926.1101, as amended, and any subsequent amendments and editions.

g. ACM from within the work area is not permitted outside of the work area except in sealed leak-tight containers.

h. Any person exiting or any equipment or machinery being removed from the contaminated work area shall be thoroughly decontaminated. If equipment or machinery is not or cannot be thoroughly decontaminated, it shall be sealed in leak-tight containers. No visible residue shall appear on the outside surface of the container.

3. Cleanup.
a. Each owner/operator engaged in a renovation abatement project subject to this Section shall ensure that:
(1) Following abatement, a visual inspection of the abated substrate is performed.

(2) A coating of a compatible encapsulating agent is applied to porous surfaces that have been stripped and cleaned of ACM. The encapsulant must be allowed to thoroughly dry prior to additional cleaning or final air clearance.

(3) The air sampler or the owner's representative inspects the abated area prior to final clearance. If there is any evidence of contamination, the asbestos contractor shall perform additional wet cleaning and HEPA vacuuming.

(4) All polyethylene sheeting, except for critical barriers and the decontamination enclosure system, is removed and disposed of as asbestos-contaminated waste.

(5) With only the critical barriers and decontamination enclosure system left in place, the entire work area, including any duct work, is wet-cleaned and HEPA vacuumed until no visible residue remains.

(6) Areas exceeding clearance standards are re-cleaned by the contractor using wet methods and HEPA vacuuming. Re-cleaning, drying, and retesting shall be repeated until the satisfactory clearance standard is achieved.

(7) Following satisfactory clearance of the work area, remaining polyethylene critical barriers and decontamination enclosure systems are removed and disposed of as asbestos-contaminated waste.

(8) Portable decontamination trailers are cleaned and polyethylene sheeting disposed of as contaminated waste.

b. Re-establishment of the work area shall only occur following completion of clean-up procedures and after clearance air monitoring has been performed and documented to the satisfaction of the air sampler or of the facility owner or his representative.

c. Replacement materials shall only be installed following completion of abatement. This does not include outdoor projects subject to this regulation.

4. Disposal.

The disposal requirements of the Disposal Section of this regulation shall apply.

D. Air Sampling and Analysis Procedures.

The background, daily, and clearance air monitoring requirements of the Air Sampling Section of this regulation shall apply.

Disclaimer: These regulations may not be the most recent version. South Carolina may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.