Section 61-79.270.H.165 - When may I begin physical construction of new units permitted under the RAP?

Universal Citation: SC Code Regs 61-79.270.H.165
Current through Register Vol. 48, No. 9, September 27, 2024

You must not begin physical construction of new units permitted under the RAP for treating, storing or disposing of hazardous remediation waste before receiving a finally effective RAP.

Disclaimer: These regulations may not be the most recent version. South Carolina may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.