(a) A surface impoundment must be removed from service in accordance with paragraph (b) of this section when:
(b) When a surface impoundment must be removed from service as required by paragraph (a) of this section, the owner or operator must:
(c) As part of the contingency plan required in R.61-79.264 Subpart D, the owner or operator must specify a procedure for complying with the requirements of paragraph (b) of this section.
(d) No surface impoundment that has been removed from service in accordance with the requirements of this section may be restored to service unless the portion of the impoundment which was failing is repaired and the following steps are taken:
(e) A surface impoundment that has been removed from service in accordance with the requirements of this section and that is not being repaired must be closed in accordance with the provisions of Section264.228.