South Carolina Code of Regulations
Chapter 61 - DEPARTMENT OF HEALTH AND ENVIRONMENTAL CONTROL
Subchapter 61-79 - Hazardous Waste Management Regulations
Part 61-79.261 - IDENTIFICATION AND LISTING OF HAZARDOUS WASTE
Subpart H - FINANCIAL REQUIREMENTS FOR MANAGEMENT OF EXCLUDED HAZARDOUS SECONDARY MATERIALS
Section 61-79.261.H.142 - Cost estimate
Current through Register Vol. 48, No. 9, September 27, 2024
(a) The owner or operator must have a detailed written estimate, in current dollars, of the cost of disposing of any hazardous secondary material as listed or characteristic hazardous waste, and the potential cost of closing the facility as a treatment, storage, and disposal facility.
(b) During the active life of the facility, the owner or operator must adjust the cost estimate for inflation within sixty (60) days prior to the anniversary date of the establishment of the financial instrument(s) used to comply with section 261.143. For owners and operators using the financial test or corporate guarantee, the cost estimate must be updated for inflation within thirty (30) days after the close of the firm's fiscal year and before submission of updated information to the Department as specified in section 261.143(e)(3). The adjustment may be made by recalculating the cost estimate in current dollars, or by using an inflation factor derived from the most recent Implicit Price Deflator for Gross National Product published by the U.S. Department of Commerce in its Survey of Current Business, as specified in paragraphs (b)(1) and (2) of this section. The inflation factor is the result of dividing the latest published annual Deflator by the Deflator for the previous year.
(c) During the active life of the facility, the owner or operator must revise the cost estimate no later than thirty (30) days after a change in the facility's operating plan or design that would increase the costs of conducting the activities described in paragraph (a) or no later than sixty (60) days after an unexpected event which increases the cost of conducting the activities described in paragraph (a) of this section. The revised cost estimate must be adjusted for inflation as specified in paragraph (b) of this section.
(d) The owner or operator must keep the following at the facility during the operating life of the facility: The latest cost estimate prepared in accordance with paragraphs (a) and (c) and, when this estimate has been adjusted in accordance with paragraph (b), the latest adjusted cost estimate.