Current through Register Vol. 48, No. 9, September 27, 2024
The following regulation will not supersede any state or
federal requirements nor special permit conditions, unless this regulation
would impose a more restrictive emission limit. The owner or operator shall
comply with all terms, conditions, and limitations of any Department-issued
permit for sources or activities at the owner or operator's facility. A
source's permit status may change upon promulgation of new regulatory
requirements.
(A) Construction Permits
(1) Applicability
(a) Except as allowed under Section
II(A)(1)(b) and (A)(1)(c) below, any person who plans to construct, alter, or
add to a source of air contaminants, including installation of any device for
the control of air contaminant discharges, shall first obtain a construction
permit from the Department prior to commencement of construction.
(b) The Department may grant permission to
proceed with minor alterations or additions without issuance of a construction
permit when the Department determines that the alteration or addition will not
increase the quantity and will not alter the character of the source's
emissions.
(c) The owners or
operators of sources not requesting to use federally enforceable construction
permit conditions to limit potential to emit, sources not subject to
regulations with more stringent start of construction limitations, or sources
not otherwise exempt from permit requirements, may undertake the following
on-site activities prior to obtaining a construction permit:
(i) Planning;
(ii) Engineering and design;
(iii) Geotechnical investigation;
(iv) Site land clearing and
grading;
(v) Setting up temporary
trailers to house construction staff and contractor personnel;
(vi) Ordering of equipment and
materials;
(vii) Receipt and
storing of equipment;
(viii)
Pouring of the foundation up to and including the mounting pads and slab on
grade;
(ix) Relocation of
utilities;
(x) For existing
sources, relocation/installation of piping, electrical service, and
instrumentation;
(xi) Temporary
power for the site (such as power lines);
(xii) Site drainage including ditches and
culverts;
(xiii) Temporary
dewatering activities associated with the excavations;
(xiv) Temporary gravel (Right Out of Crusher
(ROC)) road beds for the site;
(xv)
Soil only excavations;
(xvi)
Temporary telecommunications for the site (such as telephone and internet);
and
(xvii) Security fencing related
to the storage of equipment and materials.
(d) In the event that the source does not
qualify for issuance of a construction permit, the owners or operators accept
the financial risk of commencing the activities listed in Section
II(A)(1)(c)(i) through (A)(1)(c)(xvii) above.
(2) No permit to construct or modify a source
will be issued if emissions interfere with attainment or maintenance of any
state or federal standard.
(3) The
owner or operator shall submit written notification to the Department of the
date construction is commenced, postmarked within thirty (30) days after such
date, and written notification of the actual date of initial startup of each
new or altered source, postmarked within fifteen (15) days after such
date.
(4) Approval to construct
shall become invalid if construction:
(a) Is
not commenced within eighteen (18) months after receipt of such
approval;
(b) Is discontinued for a
period of eighteen (18) months or more; or
(c) Is not completed within a reasonable time
as deemed by the Department.
(5) The Department may extend the
construction permit for an additional 18-month period upon a satisfactory
showing that an extension is justified. This provision does not apply to the
time period between construction of the approved phases of a phased
construction project; each phase must commence construction within eighteen
(18) months of the projected and approved commencement date.
(B) Exemptions from the
Requirement to Obtain a Construction Permit
(1) No construction permits shall be required
for the sources listed in Section II(B)(1)(a) through (B)(1)(c) below, which
burn virgin fuel and which were constructed prior to February 11, 1971, and
which are not located at a facility that meets the definition of a major source
as defined in Regulation
61-62.70.2(r);
however, modifications at these facilities may trigger the requirement to
obtain a construction permit.
(a) Natural gas
boilers.
(b) Oil-fired boilers of
50 million British thermal unit per hour (Btu/hr) rated input capacity or
smaller.
(c) Coal-fired boilers of
20 million Btu/hr rated input capacity or smaller.
(2) No construction permits shall be required
for the sources listed in Section II(B)(2)(a) through (B)(2)(h) below, unless
otherwise specified by Regulation 61-62.70 or any other state or federal
requirement. A source's exemption status may change upon the promulgation of
new regulatory requirements applicable to any of the sources listed in Section
II(B)(2)(a) through (B)(2)(g), or to any other sources that have been
determined to have total uncontrolled emissions less than the thresholds in
Section II(B)(2)(h), or to any similar sources that have been granted an
exemption by the Department.
(a) Boilers and
space heaters of less than 1.5 million Btu/hr rated input capacity which burn
only virgin liquid fuels or virgin solid fuels.
(b) Boilers and space heaters of less than 10
million Btu/hr rated input capacity which burn only virgin gas fuels.
(c) Comfort air-conditioning or ventilation
systems.
(d) Motor
vehicles.
(e) Laboratory
hoods.
(f) Emergency power
generators as described below:
(i) Generators
of less than or equal to 150 kilowatt (kW) rated capacity.
(ii) Generators of greater than 150 kW rated
capacity designated for emergency use only and are operated a total of 500
hours per year or less for testing and maintenance and have a method to record
the actual hours of use such as an hour meter.
(g) Sources emitting only steam, air,
nitrogen, oxygen, carbon dioxide, or any physical combination of
these.
(h) Sources with a total
uncontrolled potential to emit (PTE) of less than five (5) tons per year each
of particulates, sulfur dioxide, nitrogen oxides, and carbon monoxide; and a
total uncontrolled PTE of less than 1000 pounds per month (lbs/month) of VOCs
will not require construction permits. Unless otherwise exempt, sources may be
exempted under this section at higher emission levels if there is a
demonstration that there are no applicable limits or requirements. These
applicable requirements include federally applicable limits or requirements.
However, these sources may be required to be included in any subsequent
construction or operating permit review to ensure that there is no cause or
contribution to an exceedance of any ambient air quality standard or limit. For
toxic air pollutant exemptions, refer to Regulation 61-62.5, Standard No. 8.
Emissions calculations and any other information necessary to document
qualification for this exemption must be maintained onsite and provided to the
Department upon request.
(3) The Department will place the exempt
sources listed in Section II(B)(2)(a) through (B)(2)(g) above, and other
sources that have been determined will not interfere with the attainment or
maintenance of any state or federal standard, on a list of sources to be
exempted without further review. The Department may develop emission thresholds
for exemption that have been determined will not interfere with the attainment
or maintenance of any state or federal standard, to be maintained with the list
of sources to be exempted without further review. This list of sources and
source emission thresholds that are exempt without further review from the
requirement to obtain a construction permit will be maintained by the
Department and periodically published in the South Carolina State Register for
use by the public and the regulated community. Requests to the Department may
be made to add sources to the list.
(4) Sources with only fugitive emissions must
submit source information, and the need for permit(s) will be made by the
Department on a case-by-case basis. This determination will take into
consideration, but will not be limited to, the nature and amount of the
pollutants, location, proximity to residences and commercial establishments,
etc.
(5) Sources of VOCs greater
than 1000 lbs/month may not require a permit. This determination will take into
consideration, but will not be limited to, applicability to state and federal
requirements. No waiver will be permissible if federal requirements apply
unless otherwise exempt. Emissions calculations and any other information
necessary to document qualification for this exemption and the need for
permit(s) will be made by the Department on a case-by-case basis. Exempt
sources of VOCs may be required to be included in any subsequent construction
or operating permit review to ensure that there is no cause or contribution to
an exceedance of any ambient air quality standard or limit.
(6) Requests for exemption from the
requirement to obtain a construction permit, for new sources similar to sources
already on the Department maintained list established in Section II(B)(3)
above, or for modifications to existing equipment, including the
reconstruction, relocation, and replacement of existing equipment, which may
qualify for exemption as per Section II(B)(2)(h) and Section II(B)(4) above,
shall include the following information:
(a) A
complete description of the existing equipment and proposed
modification;
(b) The pollutant(s)
being emitted and any deviation from the parameters provided in earlier permit
applications, permit exemptions, and issued permits;
(c) Any ambient air quality demonstrations
needed for Regulation 61-62.5, Standards No. 2, No. 7, and No. 8; and
(d) A regulatory review to demonstrate the
project is not a CAA Title I modification nor subject to Regulation 61-62.5,
Standards No. 7 and No. 7.1.
(7) The construction permitting exemptions in
Section II(B) do not relieve the owner or operator of any source from any
obligation to comply with any other applicable requirements. The Department
reserves the right to require a construction permit, and the need for permit(s)
will be made by the Department on a case-by-case basis. This determination will
take into consideration, but will not be limited to, the nature and amount of
the pollutants, location, proximity to residences and commercial
establishments, etc.
(C)
Construction Permit Applications
(1)
Construction permit applications shall be reviewed, signed, and sealed by a
professional engineer registered to practice in the State of South Carolina
(except professional engineers employed by the federal government preparing
applications for the federal government or other professional engineers
exempted from the state registration requirements).
(2) The following are exempt from the
requirement that the construction permit applications be reviewed, signed, and
sealed by a registered professional engineer provided the proposed unit is
identical to a prototype model which has been previously designed or otherwise
certified by a professional engineer:
(a)
Package-type incinerators of 750 lb/hr rated capacity or smaller which burn
Types 0 and 1 wastes as defined by the Incinerator Institute of
America;
(b) Package-type
incinerators of 500 lb/hr rated capacity or smaller which burn animal remains
excluding those remains that are considered infectious waste;
(c) Package-type boilers of 100 million
Btu/hr input capacity or smaller which burn natural gas or virgin oil as fuel;
and
(d) Package-type concrete batch
plants that are designed to be hauled to a site, set up, and broken down
quickly, with little to no additional equipment needed to manufacture
product.
(3)
Construction permit applications shall provide the information described in
Section II(C)(3)(a) through (C)(3)(r). This information should be submitted on
Department forms, but project specific information may need to be provided in
addition to that requested in applicable forms.
(a) The facility name (the name used to
identify the facility at the location requesting the permit);
(b) The location of the facility including
its street address;
(c) The name,
mailing address, e-mail address, and telephone number of the owner or operator
for the facility;
(d) The name,
mailing address, e-mail address, and telephone number of the facility's air
permit contact person;
(e) The
facility's Federal Employer Identification Number or Federal Tax ID
Number;
(f) A description and the
U. S. Standard Industrial Classification (SIC) Code and North American Industry
Classification System (NAICS) Code of the products or product lines to be
produced by the proposed sources covered by this application;
(g) The facility's planned operating
schedules;
(h) A description of the
facility's proposed new or altered processes, including the physical and
chemical properties and feed rate of the materials used and produced (in pounds
per hour), from which the facility determined potential emissions;
(i) A process flow diagram/production process
layout of all new or altered sources showing the flow of materials and
intermediate and final products. The process flow diagram/production process
layout must identify all equipment, machines, and process steps or product
lines within the production process; all product streams; all exhaust streams
(emission points) including fugitive within the production process; all waste
streams; and all control devices including inherent process control devices
used within the production process;
(j) A detailed description of each proposed
or existing source that is being altered, including the size and type along
with the make and model of the source and any associated air pollution control
equipment;
(k) A description,
including physical and chemical properties and the Chemical Abstract Service
(CAS) number (if applicable), of all emissions from each proposed source or
existing source that is being altered. Mass emission data and emission
calculations, including the potential uncontrolled and controlled mass emission
rate of each criteria pollutant and other air contaminants such as VOCs, toxic
air pollutants (TAPs), and HAPs, that will be emitted from each source covered
by the application. Emission calculations must be based on proper documentation
that supports the basis of the emission rates such as stack test data, AP-42
emission factors, material balance, and/or engineering estimates. All
assumptions used in the emission calculations must be provided. Fugitive
emissions (for example, emissions from filling operations, pumps, valves,
flanges, etc.) must be included in the emission calculations;
(l) A description of all air pollution
control devices or systems on the new or altered sources, whether inherent or
add-on. The description shall include, but not be limited to, the manufacturer
specifications and ratings, the engineering design and operating
characteristics, the projected capture and destruction, the control or removal
efficiencies at expected contaminant loading levels, and the monitoring data
collection and recordkeeping necessary to ensure proper operation of the air
pollution control devices;
(m)
Source information and calculations to demonstrate compliance with "Good
Engineering Practice Stack Height" rules;
(n) A description of each stack or vent
related to the proposed and/or existing source(s), including the minimum
anticipated height above ground, maximum anticipated internal dimensions,
discharge orientation, exhaust volume flow rate, exhaust gas temperature, and
rain protection device, if any;
(o)
Scale drawings showing a plan view of the property lines, the location of the
source, all stacks, and other emission points related to the source, as well as
buildings that might affect dispersion of any emissions;
(p) An air dispersion modeling analysis or
other information demonstrating that emissions from the facility, including
those in the application, will not interfere with the attainment or maintenance
of any ambient air quality standard;
(q) A summary of facility-wide potential
uncontrolled and controlled emissions with a regulatory applicability
determination; and
(r) Other
information as may be necessary for proper evaluation of the source as
determined by the Department.
(D) General Construction Permits
(1) The Department may develop and issue
general construction permits applicable to similar sources for new construction
projects or minor modifications to existing sources.
(2) Any general construction permit shall
incorporate all requirements applicable to the construction of similar sources
and shall identify criteria by which sources may qualify for coverage under a
general construction permit.
(3)
Coverage under a General Construction Permit
(a) Sources may submit a construction permit
application to the Department with a request for coverage under the conditions
and terms of a general construction permit for similar sources. The Department
shall grant a general construction permit to sources certifying qualification
for and agreeing to the conditions and terms of a general construction permit
for similar sources.
(b) A source
that has submitted an individual construction permit application to the
Department and has not requested coverage under the conditions and terms of a
general construction permit for similar sources, but which is determined to
qualify for coverage under a general construction permit, may be granted
coverage under the general construction permit at the sole discretion of the
Department.
(4) A source
shall be subject to enforcement action for operation without a valid permit if
the source is later determined not to qualify for coverage under a general
construction permit.
(5) The
Department may grant a source authorization to operate under a general
construction permit, but such a grant shall be a final permit action for
purposes of judicial review.
(6)
The permit application for general construction permits may deviate from the
requirements of Section II(C) above, provided that such application includes
all information necessary to determine qualification for, and to assure
compliance with, the general permit.
(7) A source that qualifies for coverage
under a Department issued general construction permit may submit a construction
permit application to the Department and request an individual construction
permit in lieu of coverage under a general construction permit.
(E) Synthetic Minor Construction
Permits
(1) General Provisions
(a) Any stationary source may request to use
federally enforceable permit conditions to limit the source's potential to emit
and become a synthetic minor source.
(b) Stationary sources requesting a synthetic
minor construction permit shall submit a complete permit application package to
the Department as prescribed by Section II(E)(5) below.
(c) Stationary sources requesting a synthetic
minor construction permit shall undergo the public participation procedures of
Section II(N) below.
(d) The
Department shall act, within a reasonable time, on an application for a
synthetic minor construction permit and shall notify the applicant in writing
of its approval, conditional approval, or denial.
(e) In the event of a denial of a synthetic
minor construction permit application, the Department shall notify the
applicant in writing of the reasons for the denial. The Department shall not
accept a subsequent synthetic minor construction permit application until the
applicant has addressed the concerns specified by the Department which caused
the denial. The source shall correct all deficiencies noted by the Department
within sixty (60) calendar days of receiving notice of the denial, or submit a
complete major source construction permit application, as prescribed by Section
II(C) above, if the source desires to proceed with the project.
(2) New Sources and Modifications
(a) A stationary source desiring to restrict
its potential to emit shall submit a written request to the Department for a
federally enforceable construction permit conditioned to constrain the
operation of the source, along with a completed construction permit application
package as prescribed by Section II(E)(5) below. The construction of the new or
modified source shall not commence until the source has received an effective
permit to construct.
(b) The owner
or operator shall submit written notification to the Department of the date
construction is commenced, postmarked within thirty (30) days after such date,
and written notification of the actual date of initial startup of each new or
altered source, postmarked within fifteen (15) days after such date. A written
request to obtain an operating permit shall be submitted to the Department
within fifteen (15) days after the actual date of initial startup of each new
or altered source in accordance with Section II(F) below. A satisfactory
compliance inspection by a Department representative may precede the issuance
of an operating permit for any newly constructed or modified source.
(3) Synthetic Minor Construction
Permit Conditions
(a) Synthetic minor
construction permits shall contain the standard permit conditions listed in
Section II(J)(1) below and any special permit conditions required to verify a
source's compliance with the emissions limitations and operational
requirements.
(b) The limitations
and requirements listed as permit conditions shall be permanent, quantifiable,
or otherwise enforceable as a practical matter.
(c) All synthetic minor construction permit
conditions that constrain the operation of a source in an effort to limit
potential to emit below major source threshold levels shall be federally
enforceable. Unless otherwise agreed by the Department and EPA, the Department
shall provide to EPA on a timely basis a copy of each proposed (or draft) and
final permit intended to be federally enforceable.
(4) General Synthetic Minor Construction
Permits
(a) The Department may, after notice
and opportunity for public participation provided under Section II(N) below,
issue a general synthetic minor construction permit applicable to similar
sources.
(b) Any general synthetic
minor construction permit shall incorporate all requirements applicable to the
construction of similar synthetic minor sources and shall identify criteria by
which sources may qualify for coverage under a general synthetic minor
construction permit.
(c) Coverage
under a General Synthetic Minor Construction Permit
(i) Sources may submit a synthetic minor
construction permit application to the Department with a request for coverage
under the conditions and terms of a general synthetic minor construction permit
for similar sources. The Department shall grant a general synthetic minor
construction permit to sources certifying qualification for and agreeing to the
conditions and terms of a general synthetic minor construction permit for
similar sources.
(ii) A source that
has submitted an individual synthetic minor construction permit application and
has not requested coverage under the conditions and terms of a general
synthetic minor construction permit for similar sources, but which is
determined to qualify for coverage under a general synthetic minor construction
permit, may be granted coverage under the general synthetic minor construction
permit at the sole discretion of the Department.
(d) The source shall be subject to
enforcement action for operation without a valid permit if the source is later
determined not to qualify for coverage under a general synthetic minor
construction permit.
(e) The
Department may grant a source authorization to operate under a general
synthetic minor construction permit without further public notice, but such a
grant shall be a final permit action for purposes of judicial review.
(f) The Department shall provide timely
notice to the public of any authorization given to a facility to operate under
the terms of a general synthetic minor construction permit. Such notice may be
made on a periodic, summarized basis covering all facilities receiving
authorization since the last notice.
(g) A source that qualifies for coverage
under a Department issued general synthetic minor construction permit may
submit a construction permit application to the Department and request an
individual synthetic minor construction permit in lieu of coverage under a
general synthetic minor construction permit.
(5) Requirements for Synthetic Minor
Construction Permit Applications
(a) In
addition to the minimum information required by Section II(C)(3) above, any
facility applying for a synthetic minor construction permit must also provide
the following:
(i) Potential emission
calculations and proposed federally enforceable emission limitations for each
emission unit at the facility verifying that the total emissions at the
facility will be below the major source (or facility) thresholds;
(ii) All proposed production and/or
operational limitations that will constrain the operation of each emission unit
that are to be identified as federally enforceable; and
(iii) All proposed monitoring parameters,
recordkeeping, and reporting requirements the applicant will use to determine
and verify compliance with the requested federally enforceable limitations on a
continuous basis. The applicant shall also provide the compliance status of
these proposed parameters and requirements at the time of the application
submittal.
(b) The
permit application for general synthetic minor construction permits may deviate
from the requirements of Section II(E)(5)(a) provided that such application
includes all information necessary to determine qualification for, and to
assure compliance with, the general permit.
(F) Operating Permits
(1) The owner or operator shall submit
written notification to the Department of the actual date of initial startup of
each new or altered source, postmarked within fifteen (15) days after such
date. Any source that is required to obtain an air quality construction permit
issued by the Department must obtain an operating permit when the new or
altered source is placed into operation and shall comply with the requirements
of this section.
(2) When a
Department issued construction permit includes only emission limits,
monitoring, reporting, and/or other requirements that do not establish
engineering or construction specifications for the project, the owner or
operator may operate the source in compliance with the terms and conditions of
the construction permit until the operating permit is issued by the
Department.
(3) When a Department
issued construction permit includes engineering and/or construction
specifications, the owner/operator or professional engineer in charge of the
project shall certify that, to the best of his/her knowledge and belief and as
a result of periodic observation during construction, the construction under
application has been completed in accordance with the specifications agreed
upon in the construction permit issued by the Department. If construction is
certified as provided above, the owner or operator may operate the source in
compliance with the terms and conditions of the construction permit until the
operating permit is issued by the Department. If construction is not built as
specified in the permit application and associated construction permit(s), the
owner/operator must submit to the Department a complete description of
modifications that are at variance with the documentation of the construction
permitting determination prior to commencing operation. Construction variances
that would trigger additional requirements that have not been addressed prior
to start of operation shall be considered construction without a
permit.
(4) Request for a New or
Revised Operating Permit
(a) For sources
covered by an effective Title V operating permit, the modification request
required by Regulation 61-62.70 shall serve as the request to operate for the
purposes of this regulation.
(b)
For sources not subject to Regulation 61-62.70, or not yet covered by an
effective Title V operating permit, the owner or operator shall submit a
written request for a new or revised operating permit to cover any new, or
altered source, postmarked within fifteen (15) days after the actual date of
initial startup of each new or altered source.
(c) The written request for a new or revised
operating permit must include, at a minimum, the following information:
(i) A list of sources that were placed into
operation; and
(ii) The actual date
of initial startup of each new or altered source.
(5) General Operating Permits
(a) The Department may develop and issue a
general operating permit applicable to similar sources.
(b) Any general operating permit shall
incorporate all requirements applicable to the operation of similar sources and
shall identify criteria by which sources may qualify for coverage under a
general operating permit.
(c)
Coverage under a General Operating Permit
(i)
Sources may submit a permit application to the Department with a request for
coverage under the conditions and terms of a general operating permit for
similar sources. The Department shall grant a general operating permit to a
source certifying qualification for and agreeing to the conditions and terms of
a general operating permit for similar sources.
(ii) A source that has submitted an
individual permit application to the Department and has not requested coverage
under the conditions and terms of a general operating permit for similar
sources, but which is determined to qualify for coverage under a general
operating permit, may be granted coverage under the general operating permit at
the sole discretion of the Department.
(d) The source shall be subject to
enforcement action for operation without a valid permit if the source is later
determined not to qualify for coverage under a general operating
permit.
(e) The Department may
grant a source authorization to operate under a general operating permit, but
such a grant shall be a final permit action for purposes of judicial
review.
(f) A source that qualifies
for coverage under a Department issued general operating permit may submit an
operating permit application to the Department and request an individual
operating permit in lieu of coverage under a general operating
permit.
(G)
Conditional Major Operating Permits
(1) The
requirements of Section II(G) shall apply to those sources that request a
federally enforceable permit to limit their potential to emit to less than
major source thresholds.
(2)
General Provisions
(a) Any stationary source
that satisfies the definition of a major source may request a federally
enforceable conditional major operating permit to limit the source's potential
to emit and become a conditional major source. Any stationary source that has
received a synthetic minor construction permit to limit the source's potential
to emit below major source threshold levels, that is not required to obtain a
Title V operating permit, shall be issued a conditional major operating permit
to consolidate the source's limitations on potential to emit and shall be
considered a conditional major source.
(b) Stationary sources requesting a
conditional major operating permit shall submit a complete request for a new or
revised operating permit to the Department as required by Section II(G)(6)
below.
(c) Stationary sources
requesting an original conditional major operating permit shall undergo the
public participation procedures of Section II(N) below.
(d) The Department shall act on a request for
a conditional major operating permit and shall notify the source in writing of
its approval, conditional approval, or denial.
(e) In the event of a denial of a conditional
major operating permit request, the Department shall notify the source in
writing of the reasons for the denial. The Department shall not accept a
subsequent conditional major operating permit request until the source has
addressed the concerns specified by the Department which caused the original
denial. The source shall correct all deficiencies noted by the Department or
submit a complete permit application in accordance with Regulation 61-62.70 in
order to receive a Title V operating permit.
(3) Existing Sources
(a) Any owner or operator desiring to be
permitted as a conditional major source shall submit an operating permit
request containing the information identified in Section II(G)(6) below. A
federally enforceable conditional major operating permit shall constrain the
operations of the source such that potential emissions fall below applicable
regulatory levels and therefore exclude the source from the requirements to
have a Title V operating permit.
(b) A request for a conditional major
operating permit shall not relieve a source from the requirement to meet the
deadline for submittal of a Title V operating permit application.
(4) New or Modified Sources
(a) Any owner or operator who plans to
construct, alter, or add to a source of air contaminants, including the
installation of any device for the control of air contaminant discharges, and
desires a conditional major operating permit shall provide a written request to
the Department for a federally enforceable synthetic minor construction permit
conditioned to constrain the operation of the source, along with a complete
construction permit application package containing the information identified
in Section II(G)(6) below. The construction of the new or modified source shall
not commence until the source has received an effective permit to construct
from the Department.
(b) A written
request to obtain a conditional major operating permit shall be submitted to
the Department, postmarked within fifteen (15) days after the actual date of
initial startup of each new or altered source. This request shall include any
additional information required in Section II(G)(6) below. These facilities
will be issued conditional major operating permits without further public
notice if no substantive changes to limitations are required. A satisfactory
compliance inspection by a Department representative may precede the issuance
of an operating permit for any newly constructed or modified source.
(5) Conditional Major Operating
Permit Conditions
(a) Conditional major
operating permits shall contain the standard permit conditions listed in
Section II(J)(1) below, and any special permit conditions required to verify a
source's compliance with the emissions limitations and operational
requirements.
(b) The limitations
and requirements listed as permit conditions shall be permanent, quantifiable,
or otherwise enforceable as a practical matter.
(c) All conditional major operating permit
conditions that constrain the operation of a source in an effort to limit
potential to emit below major source threshold levels as defined in Regulation
61-62.70 shall be federally enforceable. Unless otherwise agreed by the
Department and EPA, the Department shall provide to EPA on a timely basis a
copy of each proposed (or draft) and final permit intended to be federally
enforceable.
(6)
Additional Requirements for Conditional Major Operating Permit Requests
(a) In addition to the minimum information
required by Section II(C)(3) above, any facility requesting a conditional major
operating permit must also provide the following:
(i) Potential emission calculations and
proposed federally enforceable emission limitations for each emission unit at
the facility verifying that the total emissions at the facility will be below
the major source (or facility) thresholds;
(ii) All proposed production and/or
operational limitations that will constrain the operation of each emission unit
that are to be identified as federally enforceable; and
(iii) All proposed monitoring parameters,
recordkeeping, and reporting requirements the source will use to determine and
verify compliance with the requested federally enforceable limitations on a
continuous basis. The source shall also provide the compliance status of these
proposed parameters and requirements at the time of the request
submittal.
(b) The
request for general conditional major operating permits may deviate from the
requirements of Section II(G)(6) provided that such request includes all
information necessary to determine qualification for, and to assure compliance
with, the general permit.
(7) General Conditional Major Operating
Permits
(a) The Department may, after notice
and opportunity for public participation provided under Section II(N) below,
issue a general conditional major operating permit applicable to similar
sources.
(b) Any general
conditional major operating permit shall incorporate all requirements
applicable to the operation of similar conditional major sources and shall
identify criteria by which sources may qualify for a general permit.
(c) Coverage under a General Conditional
Major Operating Permit
(i) Sources may submit
a permit application to the Department with a request for coverage under the
conditions and terms of a general conditional major operating permit for
similar sources. The Department shall grant a general conditional major
operating permit to sources certifying qualification for and agreeing to the
conditions and terms of a general conditional major operating permit for
similar sources.
(ii) A source that
has submitted an individual permit application to the Department and has not
requested coverage under the conditions and terms of a general conditional
major operating permit for similar sources, but which is determined to qualify
for coverage under a general conditional major operating permit, may be granted
coverage under the general conditional major operating permit at the sole
discretion of the Department.
(d) The source shall be subject to
enforcement action for operation without a valid permit if the source is later
determined not to qualify for coverage under a general conditional major
operating permit.
(e) The
Department may grant a source authorization to operate under a general
conditional major operating permit without further public notice, but such a
grant shall be a final permit action for purposes of judicial review.
(f) The Department shall provide timely
notice to the public of any authorization given to a facility to operate under
the terms of a general conditional major operating permit. Such notice may be
made on a periodic, summarized basis covering all facilities receiving
authorization since the last notice.
(g) A source that qualifies for coverage
under a Department issued general conditional major operating permit may submit
a permit application to the Department and request an individual conditional
major operating permit in lieu of coverage under a general conditional major
operating permit.
(H) Operating Permit Renewal Requests
(1) Submission of a request for renewal
meeting the requirements in Section II(H)(2)-(5) below, shall allow the owner
or operator to continue operating pursuant to the most recent operating permit
until such time as the Department has taken final action on the request for
renewal.
(2) Any source that wishes
to have its operating permit renewed must submit a written request to the
Department.
(3) The provisions of
Section II(H) shall apply only to those sources not subject to Regulation
61-62.70. For sources covered by an effective Title V operating permit, the
operating permit renewal request required by Regulation 61-62.70 shall serve as
the request to operate for the purposes of this regulation.
(4) For sources not subject to Regulation
61-62.70, the owner or operator shall submit an operating permit renewal
request to the Department within ninety (90) days prior to the operating permit
expiration date. The source may be inspected by the Department in order to
decide whether to renew the permit. Past records of compliance and future
probability of compliance will be considered in making the decision regarding
renewal.
(5) Operating permit
renewal requests shall include a description of any changes at the facility
that have occurred since issuance of the last operating permit that may affect
the operating permit or operating permit review. In general, the description
shall include any addition, alteration, or removal of sources, including
sources exempt from construction permit requirements; addition, alteration, or
removal of emission limitations; any changes to monitoring, recordkeeping, or
reporting requirements; and any changes or additions to special permit
conditions. The following items should be addressed as part of the operating
permit renewal request:
(a) The facility name
(the name used to identify the facility at the location requesting the
permit);
(b) The location of the
facility including its street address;
(c) The name, mailing address, e-mail
address, and telephone number of the owner or operator for the
facility;
(d) The name, mailing
address, e-mail address, and telephone number of the facility's air permit
contact person;
(e) The facility's
Federal Employer Identification Number or Federal Tax ID Number;
(f) Any change to the SIC Code or NAICS Codes
of the products or product lines;
(g) Any construction permits to be
incorporated into the operating permit, either whole or in part, any listed
information descriptions that have been removed or decommissioned, and any
changes to exempted sources listed in the current operating permit;
(h) Any change to the facility's planned
operating schedules or description of the facility's current and/or proposed
processes, including the physical and chemical properties and feed rate of the
materials used and produced (in lb/hr) from which the facility determined
actual and potential emissions;
(i)
Any changes to current process flow diagram or production process layout shall
be addressed, showing the flow of materials and intermediate and final
products. Updated process flow diagram or production process layout must
identify major equipment, machines, and process steps or product lines within
the production process; all product streams; all exhaust streams (emission
points) including fugitive within the production process; all waste streams;
and all control devices including inherent process control devices used within
the production process;
(j) A
description, including the CAS number (if applicable), of all emissions from
each source. Mass emission data and emission calculations, including the
potential uncontrolled and controlled mass emission rate of each criteria
pollutant and other air contaminants such as VOCs, TAPs, and HAPs emitted from
each source. Emission calculations must be based on proper documentation that
supports the basis of the emission rates such as stack test data, AP-42
emission factors, material balance, and/or engineering estimates. All
assumptions used in the emission calculations must be provided. Fugitive
emissions (for example, emissions from filling operations, pumps, valves,
flanges, etc.) must be included in the emission calculations. A summary of
facility-wide potential uncontrolled and controlled emissions with a regulatory
applicability determination must be provided. If existing data supplied to the
Department remains correct, identify documents referenced to comply with this
requirement;
(k) A description of
stack, vent, or fugitive emission parameters associated with each non-exempt
emission source. For each emission point/source, this information should
include, as appropriate, Universal Transverse Mercator or latitude and
longitude coordinates of the emission location, the minimum height above
ground, maximum internal dimensions of the emission point/vent, discharge
orientation, emission exit velocity, emission exit temperature, dimensions
describing the volume or area of fugitive emissions, existence of any rain
protection device or other impediment to vertical dispersion, etc. If existing
data supplied to the Department remains correct, identify the document(s)
submitted to comply with this requirement; and
(l) Other information as may be necessary for
proper evaluation of the operating permit request.
(I) Registration Permits
(1) Development of Registration Permits
(a) The Department may develop and issue a
registration permit applicable to similar sources.
(b) Any registration permit developed shall
incorporate all requirements applicable to the construction and operation of
similar sources and shall identify criteria by which sources may qualify for
coverage under a registration permit.
(c) Registration permits will be developed
only for specific stationary source groups with uncontrolled potential to emit
less than the threshold for major source groups, in accordance with Regulation
61-62.70, Title V Operating Permit Program; Regulation 61-62.5, Standard No. 7,
Prevention of Significant Deterioration; Regulation 61-62.5, Standard No. 7.1,
Nonattainment New Source Review; and where equipment similarities and
simplicity remove the need for in depth site-specific review.
(2) Application for Coverage Under
a Registration Permit
(a) Coverage under a
Registration Permit
(i) Sources may submit a
permit application to the Department with a request for coverage under the
conditions and terms of a registration permit for similar sources in lieu of a
construction and operating permit as provided in Section II(A) and (F) above.
The Department shall grant a registration permit to sources certifying
qualification for and agreeing to the conditions and terms of the registration
permit applicable to similar sources.
(ii) A source that has submitted an
individual permit application to the Department and has not requested coverage
under the conditions and terms of a registration permit for similar sources,
but which is determined to qualify for a registration permit, may be granted
coverage under the registration permit at the sole discretion of the
Department.
(b) The
source shall be subject to enforcement action for operation without a valid
permit if the source is later determined not to qualify for coverage under a
registration permit.
(c) The
Department reserves the right to require a construction and/or operating
permit; the requirement for a permit(s) will be made by the Department on a
case-by-case basis. This determination will take into consideration, but may
not be limited to, the nature and amount of the pollutants, location, and
proximity to residences and commercial establishments.
(d) The Department may grant a source
authorization to operate under a registration permit, but such a grant shall be
a final permit action for purposes of judicial review.
(e) A source that qualifies for coverage
under a Department issued registration permit may submit a permit application
to the Department and request an individual permit in lieu of coverage under a
general registration permit.
(3) Registration Permit Conditions
(a) Registration permits shall contain any
applicable permit conditions listed in Section II(J) below as the Department
finds appropriate.
(b) Registration
permits shall contain any applicable special permit conditions required to
verify a source's compliance with any emissions limitations and operational
requirements.
(4) Any
registration permit may be reopened by the Department for cause or to include
any new standard or regulation which becomes applicable to a source during the
life of the permit.
(J)
Permit Conditions
(1) Standard Permit
Conditions
All construction and operating permits shall contain the
following standard permit conditions.
(a) No applicable law, regulation, or
standard will be contravened.
(b)
All official correspondence, plans, permit applications, and written statements
are an integral part of the permit. Any false information or misrepresentation
in the application for a construction or operating permit may be grounds for
permit revocation.
(c) For sources
not required to have continuous emission monitors, any malfunction of air
pollution control equipment or system, process upset, or other equipment
failure which results in discharges of air contaminants lasting for one (1)
hour or more and which are greater than those discharges described for normal
operation in the permit application, shall be reported to the Department within
twenty-four (24) hours after the beginning of the occurrence and a written
report shall be submitted to the Department within thirty (30) days. The
written report shall include, at a minimum, the following:
(i) The identity of the stack and/or emission
point where the excess emissions occurred;
(ii) The magnitude of the excess emissions
expressed in the units of the applicable emission limitation and the operating
data and calculations used in determining the excess emissions;
(iii) The time and duration of the excess
emissions;
(iv) The identity of the
equipment causing the excess emissions;
(v) The nature and cause of such excess
emissions;
(vi) The steps taken to
remedy the malfunction and the steps taken or planned to prevent the recurrence
of such malfunction;
(vii) The
steps taken to limit the excess emissions; and
(viii) Documentation that the air pollution
control equipment, process equipment, or processes were at all times maintained
and operated, to the maximum extent practicable, in a manner consistent with
good practice for minimizing emissions.
(d) Sources required to have continuous
emission monitors shall submit reports as specified in applicable parts of the
permit, law, regulations, or standards.
(e) Any owner or operator who constructs or
operates a source or modification not in accordance with the application
submitted pursuant to this regulation or with the terms of any approval to
construct, or who commences construction after the effective date of these
regulations without applying for and receiving approval hereunder, shall be
subject to enforcement action.
(f)
Approval to construct shall become invalid if construction is not commenced
within eighteen (18) months after receipt of such approval, if construction is
discontinued for a period of eighteen (18) months or more, or if construction
is not completed within a reasonable time. The Department may extend the
eighteen (18)-month period upon a satisfactory showing that an extension is
justified. This provision does not apply to the time period between
construction of the approved phases of a phased construction project; each
phase must commence construction within eighteen (18) months of the projected
and approved commencement date.
(g)
A copy of the Department issued construction and/or operating permit must be
kept readily available at the facility at all times. The owner or operator
shall maintain such operational records; make reports; install, use, and
maintain monitoring equipment or methods; sample and analyze emissions or
discharges in accordance with prescribed methods at locations, intervals, and
procedures as the Department shall prescribe; and provide such other
information as the Department reasonably may require. All records required to
demonstrate compliance with the limits established under a permit shall be
maintained on site for a period of at least five (5) years from the date the
record was generated.
(2) Special Permit Conditions
As the Department finds appropriate, permits shall include
special permit conditions such as, but not limited to, production limits,
operational limits, source performance testing, operation and maintenance
requirements, notification requirements, recordkeeping requirements, reporting
requirements, and other monitoring as required.
(a) When special permit conditions contain
production or operational limits, the permit shall have monitoring and/or
recordkeeping requirements to verify a source's compliance with the
limitations.
(b) When special
permit conditions require an add-on air pollution control device to be operated
at a specified destruction and removal efficiency level, the permit shall have
monitoring and recordkeeping requirements to determine the add-on air pollution
control device's performance on a short-term basis.
(c) The time period over which a permit
limitation on production or operation extends will be as short as possible. For
the purpose of determining compliance, permit limitations will, in general, not
exceed one (1) month and shall not exceed an annual limit with a rolling
monthly average or sum.
(d) An
owner or operator of stationary sources that desires or is required to conduct
performance tests to verify emissions limitations shall ensure that source
tests are conducted in accordance with the provisions of Regulation 61-62.1,
Section IV, Source Tests.
(e) An
hourly emission limit shall be sufficient only if the permit condition(s)
require the installation, calibration, maintenance, and operation of a CEMS or
any other monitoring approved by the Department. All monitoring data shall be
defined and recorded for showing compliance with the emission
limit(s).
(f) The limitations and
requirements listed in the permit conditions shall be permanent, quantifiable,
or otherwise enforceable as a practical matter.
(K) Exceptions
(1) Upon request, the Department may alter
operating permits, compliance schedules, or other restrictions on operation of
a source provided that resulting ambient air concentration levels will not
exceed any national or state ambient air quality standard. Factors to be
considered by the Department may include, but are not limited to, technology,
economics, national energy policy, and existing air quality. The request by the
source must also show the following:
(a) Good
faith efforts have been made to comply with the state requirements;
(b) The source is unable to comply with the
state requirements because the necessary technology or other alternative
methods of control are not reasonably available or have not been available for
a sufficient period of time;
(c)
Any available operating procedures or control measures reducing the impact of
the source on ambient air concentrations have been implemented; and
(d) The request is submitted in a timely
manner.
(2) The
provisions of this paragraph shall not apply to mass emission limits which are
imposed upon any source by the following requirements:
(a) Federal New Source Performance Standards
(NSPS);
(b) National Emission
Standards for Hazardous Air Pollutants (NESHAP);
(c) Federal or State Prevention of
Significant Deterioration (PSD) Regulations; or
(d) Nonattainment requirements.
(3) Where a permanent increase in
the visible emission limitation for a source is requested, the source must
demonstrate that it will remain in compliance with the applicable particulate
emission standard.
(4) Any
alternative compliance schedule shall provide for compliance with the
applicable regulations as expeditiously as practicable based on a plan
submitted with the request for the alternative compliance schedule.
(5) Any request under this section will be
subjected to public notice and opportunity for a public hearing. Upon approval
by the Board, the recommendations of this Department shall be sent to the
Administrator, or his designated representative, for approval or
disapproval.
(6) Where alternative
compliance schedule provisions are contained elsewhere in the air pollution
control regulations, those provisions shall supersede the requirements in this
section.
(L) Emergency
Provisions
(1) An "emergency" means any
situation arising from sudden and reasonably unforeseeable events beyond the
control of the source, including acts of God, in which a situation requires
immediate corrective action to restore normal operation, and that causes the
source to exceed a technology-based emission limitation under the permit due to
unavoidable increases in emissions attributable to the emergency. An emergency
shall not include noncompliance to the extent caused by improperly designed
equipment, lack of preventative maintenance, careless or improper operation, or
operator error.
(2) An emergency
may be documented through properly signed, contemporaneous operating logs and
other relevant evidence that verify:
(a) An
emergency occurred and the owner or operator can identify the cause(s) of the
emergency;
(b) The permitted source
was, at the time the emergency occurred, being properly operated;
(c) During the period of the emergency, the
owner or operator took all reasonable steps to minimize levels of emissions
that exceeded the emission standards or other requirements in the permit;
and
(d) The owner or operator gave
a verbal notification of the emergency to the Department within twenty-four
(24) hours of the time when emission limitations were exceeded, followed by a
written report within thirty (30) days. The written report shall include, at a
minimum, the information required by Section II(J)(1)(c)(i) through
(J)(1)(c)(viii) above. The written report shall contain a description of the
emergency, any steps taken to mitigate emissions, and corrective actions
taken.
(3) This
provision is in addition to any emergency or upset provision contained in any
applicable requirement.
(M) Transfer of Ownership/Operation Within
thirty (30) days of the transfer of ownership/operation of a facility, the
current permit holder and prospective new owner/operator shall submit to the
Department a written request for transfer of the source operating or
construction permit(s). The written request for transfer of the source
operating or construction permit(s) shall include any changes pertaining to the
facility name; the name, mailing address, and telephone number of the owner or
operator for the facility; and any proposed changes to the permitted activities
of the source. Transfer of the operating or construction permit(s) will be
effective upon written approval by the Department.
(N) Public Participation Procedures
(1) When determined to be appropriate by the
Department (or specified by regulation), notice of permitting activity shall be
provided to the public and other entities for their review and comment. Public
notice shall be given by publication in a newspaper of general circulation in
the area where the source is located, or by posting to a public website
identified by the Department, or by publication in the South Carolina State
Register, and to persons on a mailing list developed by the Department,
including those who request in writing to be on the list. The Department may
use additional means of public notice, including, but not limited to public
meetings.
(2) The notice shall
include the following:
(a) The name and
physical address of the facility;
(b) The name and address of the
Department;
(c) Applicable
activities involved in the permit action;
(d) Applicable emission change involved in
any permit modification;
(e) The
name, address, and telephone number of a person from whom interested persons
may obtain additional information, including copies of the permit draft, the
application, and all other materials available to the Department that are
relevant to the permit decision, except for information entitled to
confidential treatment (the contents of any proposed or draft permit shall not
be treated as confidential information);
(f) A brief description of the comment
procedures; and
(g) The time and
place of any public hearing that may be held, including a statement of
procedures to request a hearing (unless a hearing has already been
scheduled).
(3) The
Department shall provide at least thirty (30) days for public and EPA comment
and shall give notice of any public hearing at least thirty (30) days in
advance of the hearing.
(a) The Department
shall keep a record of the commenters and the comments made during the public
comment period.
(b) The Department
shall consider all written comments submitted within a time specified in the
notice of public comment and all comments received at any public hearing(s) in
making a final decision on the approvability of the application.
(4) A newly constructed or
modified source issued a federally enforceable final construction permit will
not require an additional public comment period and/or hearing to obtain an
operating permit, unless the source proposes a change in the original
construction and/or operational plan, prior to commencing construction, which
the Department determines would require an additional public comment period
and/or hearing.
(5) Any proposed
new or modified stationary source required to undergo a public comment period
shall not commence any construction until all public participation procedures
of this section are completed, and the source has received an effective
construction permit from the Department.
(6) Maintenance activities, repairs, and
replacements which the Department determines to be routine for that source
category shall not, by themselves, be required to undergo the public
participation procedures of Section II(N).
(O) Inspection and Entry
Upon presentation of credentials and other documents as may
be required by law, the owner or operator shall allow the Department or an
authorized representative to perform the following:
(1) Enter the facility where
emissions-related activity is conducted, or where records must be kept under
the conditions of the permit;
(2)
Have access to and copy, at reasonable times, any records that must be kept
under the conditions of the permit;
(3) Inspect any facilities, equipment
(including monitoring and air pollution control equipment), practices, or
operations regulated or required under this permit; and
(4) As authorized by the Clean Air Act and/or
the South Carolina Pollution Control Act, sample or monitor, at reasonable
times, substances or parameters for the purpose of assuring compliance with the
permit or applicable requirements.