South Carolina Code of Regulations
Chapter 61 - DEPARTMENT OF HEALTH AND ENVIRONMENTAL CONTROL
Subchapter 61-58.1 - Construction and Operation Permits
Section 61-58.1.I - Delegated Review Program

Universal Citation: SC Code Regs 61-58.1.I

Current through Register Vol. 48, No. 9, September 27, 2024

(1) A public water system which meets the following criteria may apply for delegated review authority.

(a) The system must have a professional engineer on staff.

(b) The system must have a full-time management and full-time inspection and maintenance staff.

(c) The system must have a set of design criteria which has been approved by the Department.

(d) The system must have a set of approved construction specifications for water distribution lines on file with the Department. These specifications must bear the seal and signature of the professional engineer on staff.

(e) The system must have historically demonstrated satisfactory bacteriological and chemical water quality as required by R.61-58.5, R.61-58.10, and R.61-58.11.

(f) The system must have a satisfactory pressure record as required by R.61-58.4.D(4).

(g) The system must have implemented and maintained a viable cross connection control program in accordance with R.61-58.7(F)(F);

(h) The system must have an active inspection program for new water distribution line construction;

(i) The system must maintain an updated map of the distribution system. This map must include the following, where applicable:
(i) Existing water distribution lines;

(ii) Location and size of all storage tanks, booster pump stations, pressure reducing valves, master metered connections, and fire hydrants; and,

(iii) Location of all water treatment plant(s), surface water intake(s), well(s) and connections with other public water systems; and,

(j) The system must have a computerized hydraulic model of its distribution system. This model shall include a sufficient number of lines to adequately represent the distribution system. This hydraulic model must be made available for review by the Department upon request.

(2) The application for delegated review authority shall include a completed application form for a permit to construct, submitted in triplicate (one original and two copies), and necessary documentation to show compliance with the criteria specified in R.61-58.1(I)(1)(I)(1). If the system does not have approved construction specifications or design criteria on file with the Department at the time of making application for delegated review authority, the application must include two (2) copies of its standard specifications and two (2) copies of its design criteria.

(3) The Department may revoke a system's delegated review authority at any time for failure to maintain the qualifications as specified in R.61-58.1(I)(1)(I)(1) or failure to comply with the permitting procedures under the delegated review program. Such revocation is subject to appeal in accordance with the Administrative Procedures Act for contested cases.

(4) The delegated review program applies only to the permitting of line extensions which are not subject to the requirements for demonstrating viability as specified in R.61-58.1.B(4) and connecting to the system which has the delegated review authority.

(5) The procedure for obtaining a permit to construct under the delegated review program is as follows:

(a) The professional engineer for a water line extension project may submit plans and specifications and design data to the public water system with delegated review authority for review in lieu of submitting to the Department an application for a permit to construct as specified in R.61-58.I(B)(2). The delegated review authority shall review the project for compliance with its design criteria and construction specifications.

(b) Following a satisfactory review of the project by the delegated review authority, the system shall submit the following information to the Department for permitting:
(i) A transmittal letter, signed by the professional engineer on staff, which clearly states the project is being submitted under the delegated review program. This letter shall also state that the project has been reviewed and complies with the system's design criteria and construction specifications;

(ii) A completed application form for a permit to construct in duplicate (the original and one (1) copy);

(iii) Two (2) sets of plans bearing the seal and signature of the design engineer;

(iv) One (1) copy of the flow test results from a location near the tie-on site. This must include the static pressure and residual pressure while flowing in excess of the demand for the proposed extension. The time, date and duration of the flow test, the size of pipe, type pipe and distance to the tie-on site must be included;

(v) One (1) copy of design calculations indicating a minimum pressure of twenty-five (25) pounds per square inch must be maintained everywhere in the distribution system during instantaneous demand or twenty (20) pounds per square inch during fire flow plus peak hourly flow; and,

(vi) Two (2) copies of a site location map.

(c) Where applicable, the Department will review the project for consistency with the Coastal Zone Management Plan and for construction in navigable waters prior to issuing a permit to construct.

(d) Written approval must be obtained from the Department prior to placing the water line extension into service.

Disclaimer: These regulations may not be the most recent version. South Carolina may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.