South Carolina Code of Regulations
Chapter 61 - DEPARTMENT OF HEALTH AND ENVIRONMENTAL CONTROL
Subchapter 61-43 - STANDARDS FOR THE PERMITTING OF AGRICULTURAL ANIMAL FACILITIES
Part 200 - ANIMAL FACILITIES (OTHER THAN SWINE)
Section 61-43.200.90 - General Requirements for Animal Manure Lagoons, Treatment Systems, and Animal Manure Storage Ponds

Universal Citation: SC Code Regs 61-43.200.90

Current through Register Vol. 48, No. 9, September 27, 2024

A. The lagoon, treatment system, or manure storage pond shall be designed by a professional engineer or an NRCS engineer and the construction shall be certified by the design engineer or professional engineer licensed in S.C. It is a violation of these regulations and the South Carolina Pollution Control Act for the owner or operator of the facility to make modifications or physical changes to the lagoon, treatment system, or manure storage pond without the prior approval of the Department and supervision of NRCS or a professional engineer. Plans and specifications for lagoon, treatment system, or manure storage pond modifications shall be designed and certified by NRCS or a professional engineer and submitted to the Department for approval prior to the modification.

B. Animal manure lagoons and manure storage ponds shall be designed, at a minimum, to NRCS-CPS. The lagoon or manure storage pond shall be designed to provide a minimum storage for manure, wastewater, normal precipitation less evaporation, normal runoff, residual solids accumulation, capacity for the fifty (50) year-twenty-four (24) hour storm event (precipitation and associated runoff) and at least 2 feet of freeboard.

C. All lagoons and storage ponds shall be provided with a liner, designed with an initial specific discharge rate of less than 0.0156 feet/day, in order to protect groundwater quality. When lagoons or manure storage ponds are lined only using soils with low permeability rates (e.g., clay), the Department shall require appropriate documentation to demonstrate that the computed soil permeability rates of the liner are sufficiently low or certification from the preparer of the Animal Facility Management Plan that the NRCS design standards for lining lagoons and/or manure storage ponds with soils have been met. When geomembrane liners are utilized, they shall be designed, at a minimum, to meet NRCS-CPS.

D. If seepage results in either an adverse impact to groundwater or a significant adverse trend in groundwater quality occurs as determined by the Department, the lagoon or manure storage pond shall be repaired at the owner's or operator's expense. Assessment and/or additional monitoring (more wells, additional constituents, and/or increased sampling frequency) may be required by the Department to further assess the extent of the seepage. The repairs and/or assessment shall be completed in accordance with an implementation schedule approved by the Department. The Department may require groundwater corrective action.

E. Manure shall not be placed directly in or allowed to come into contact with groundwater and/or surface water. The minimum separation distance between the lowest point of the lagoon or manure storage pond and the seasonal high water table beneath the lagoon or manure storage pond is 2 feet. If a geomembrane liner is installed, the minimum separation distance is 1 foot from the seasonal high water table. Designs that include controlled drainage for water table adjustment shall be evaluated by the Department on a case-by-case basis, and may include additional monitoring and groundwater control requirements. If a design is proposed for water table adjustment, the design shall not impact wetlands.

F. Monitoring wells may be required by the Department on a case-by-case basis upon Department review of the submittal package.

G. A groundwater monitoring plan shall be submitted with the permit application to the Department. All applicable State certification requirements regarding well installation, laboratory analyses, and report preparation shall be met. Each groundwater monitoring well installed shall be permitted and shall be sampled at least once annually by qualified personnel at the expense of the permittee. The results shall be submitted to the Department in accordance with the specified permit requirements. Groundwater Sampling results shall be maintained by the producer for eight (8) years. The Department may conduct routine and random visits to the animal facility to sample the monitoring wells.

H. Prior to operation of the lagoon or manure storage pond, all monitoring wells shall be sampled in accordance with the parameters identified in the permit such that a background concentration level can be established.

I. Before the construction of a lagoon and/or a manure storage pond, the owner or operator shall remove all under-drains that exist from previous agricultural operations that are under the lagoon or manure storage pond and/or within 25 feet of the outside toe of the proposed lagoon or manure storage pond dike. This requirement does not include under-drains that are approved as a part of designs that include controlled drainage for water table adjustment.

J. Proper water levels in lagoons and manure storage ponds, as per plans and specifications, shall be maintained at all times by the permittee. The Department may require specific lagoon or manure storage pond volume requirements in permits. An approved marker shall be installed to measure water levels.

K. If a lagoon, treatment system, or manure storage pond, all of these, breaches or fails, the owner or operator of the animal facility shall immediately notify the Department, the appropriate local government officials, and the owners or operators of any potable surface water treatment plant located downstream from the animal facility that could reasonably be expected to be adversely impacted.

L. Lagoons, treatment systems, and manure storage ponds shall be completely enclosed with an acceptable fence, unless a fence waiver is obtained from the Department.

M. Lagoons and manure storage ponds shall have at least four (4) warning signs posted in the four (4) cardinal directions around the perimeter of the structure. These signs must read, "Warning - Deep and Polluted Water".

N. Vegetation on the dikes and around the lagoon, treatment system, or manure storage pond should be kept below a maximum height of 18 inches. Trees or deeply rooted plants shall be prevented from growing on the dikes or within 25 feet of the outside toe of the dikes of the lagoon, treatment system, or manure storage pond. Existing trees on the dikes shall be evaluated by NRCS staff or a dam engineer licensed in South Carolina to determine if they should be removed or remain.

O. Livestock or other animals that could cause erosion or damage to the dikes of the lagoon, treatment system, or manure storage pond shall not be allowed to enter the lagoon, treatment system, or manure storage pond, or graze on the dike or within 25 feet of the outside toe of the dike.

P. The Department shall require existing facilities, regardless of size, with a history of manure handling, treatment, and disposal problems related to a lagoon, to phase out the existing lagoon and incorporate new technology.

Disclaimer: These regulations may not be the most recent version. South Carolina may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.