South Carolina Code of Regulations
Chapter 61 - DEPARTMENT OF HEALTH AND ENVIRONMENTAL CONTROL
Subchapter 61-107 - Solid Waste Management
Subchapter 61-107.18 - Solid Waste Management: Off-site Treatment of Contaminated Soil
Section 61-107.18.C - General Provisions
Current through Register Vol. 48, No. 9, September 27, 2024
1. The siting, design, construction, operation, and closure activities for facilities that treat contaminated soil shall conform to the standards set forth in this regulation, unless otherwise approved by the Department. Engineering plans, specifications, reports and other documents approved by the Department during the review process shall become enforceable documents upon issuance of a permit pursuant to this regulation. Facilities shall be constructed as approved and permitted.
2. Prior to the construction of a new soil treatment facility, a permit shall be obtained from the Department pursuant to this regulation. Prior to the modification of an existing soil treatment facility, as-built drawings of the existing facility which have current Department approval shall be submitted in addition to plans and specifications of proposed modifications to the facility. Any modification to the design/operation of a facility that would change the language of the permit shall receive prior Department approval.
3. Prior to operation of a new permitted soil treatment facility or a permitted modification to an existing facility, the facility shall be inspected by the Department and receive operational approval.
4. The Department reserves the right to require the soil treatment facility to acquire an RD&D permit pursuant to Regulation Regulation 61-107.10 for any process or compound for which the information provided is deemed insufficient to establish the efficacy of the proposed process to the Department's satisfaction. If, after the two (2) years expiration of the RD&D permit, the process is proved to be a viable method for treating soil, a permit pursuant to this regulation may be issued for the process. Petroleum and other compounds that have been shown to be highly degradable via the proposed treatment process will not generally require a RD&D permit. A permit requested pursuant to this regulation may be denied should the process not be determined to be acceptable to the Department's satisfaction.
5. No later than six (6) months from the effective date of this regulation, existing soil treatment facilities shall submit to the Department a permit application with supporting documents as outlined in Section D of this regulation.
6. Failure to begin construction of the treatment facility within twelve (12) months of the issuance of the Department permit shall render that permit invalid.
7. Upon reasonable cause to suspect that the treatment facility and/or treatment process poses a threat to human health or the environment, the Department, upon notification to the owner/operator, may require the owner/operator to investigate and, if appropriate, develop and implement a corrective action program approved by the Department.
8. Soil treatment facilities shall demonstrate consistency with the host Region/County Solid Waste Management Plan pursuant to Section D. of this regulation.
9. Open dumping of contaminated soil is prohibited.
10. Soil treatment facilities shall adhere to Federal and State rules and regulations and local zoning, land use and other applicable local ordinances and OSHA requirements.
11. Transfer of ownership.
12. All chemical and biological analyses required by this regulation for submittal to the Department shall be analyzed by a laboratory certified by the Department for that particular parameter.
13. All analytical methods used shall be appropriate for the parameters being quantified given the sample matrix (gasoline and diesel range organics at a minimum.) Quantification of total petroleum hydrocarbons shall employ appropriate extraction methods and include both short and long chain hydrocarbons.
14. Approval from the State Toxicologist shall be required when intergeneric (i.e., bioengineered) microorganisms or pathogenic (i.e., disease-causing) microorganisms are used in the proposed technology.
15. A maintenance plan shall be submitted that describes how each major component of the soil treatment facility and all associated equipment shall be maintained at the facility, and how the facility shall be operated in accordance with its intended use.
16. It is incumbent on the soil treatment facility to ensure that any soil-like material is compatible with the approved treatment process. Any contaminants in the soil-like material shall be treated to acceptable standards.