South Carolina Code of Regulations
Chapter 19 - STATE BUDGET AND CONTROL BOARD
Article 4 - OFFICE OF GENERAL SERVICES
Section 19-450.6 - Review of Permit Application and Comment by State Agencies
Current through Register Vol. 48, No. 9, September 27, 2024
A. Review by Agencies
B. Time for Response. All State agencies receiving public notice of permit applications from the Corps of Engineers, Coast Guard or the Department must submit their comments directly to the Department within thirty (30) days of the receipt of the public notice. Requests by State agencies for extensions of time shall be submitted to the Department in writing before the expiration of the original comment period. A failure to comment, or to request an extension of time during that period shall be treated as no objection to the application. The Department may consider untimely comments for good cause shown.
C. Form and Scope of Comments. Comments and their supporting materials are used to review the proposed activity, as the basis for discussing the terms and conditions of the proposed activity, for conciliating objections, if any, by the Department in making its decision. Therefore, comments by an agency should be objective, and state specifically its conclusions concerning the permit application and include in summary form the information that supports the conclusion of the agency. Objections shall be specifically stated and contain supporting material. Comments which are without support, or are limited solely to use of adjacent private highlands, or are without a comparative assessment of the beneficial and detrimental impacts of the projected activity on lands and waters subject to the jurisdiction of the Department, may, in the discretion of the Department, be disregarded as non-responsive, or returned to the agency for reconsideration or reformulation. All comments of agencies shall be public records available to the public and applicant at the Department.