A. State Standards of Responsibility.

Factors to be considered in determining whether the state standards of responsibility have been met include whether a prospective contractor has:

(1) available the appropriate financial, material, equipment, facility, and personnel resources and expertise, or the ability to obtain them, necessary to indicate its capability to meet all contractual requirements;

(2) a satisfactory record of performance;

(3) a satisfactory record of integrity;

(4) qualified legally to contract with the State; and

(5) supplied all necessary information in connection with the inquiry concerning responsibility.

B. Obtaining Information; Duty of Contractor to Supply Information.

At any time prior to award, the prospective contractor shall supply information requested by the procurement officer concerning the responsibility of such contractor. If such contractor fails to supply the requested information, the procurement officer shall base the determination of responsibility upon any available information or may find the prospective contractor non responsible if such failure is unreasonable. In determining responsibility, the procurement officer may obtain and rely on any sources of information, including but not limited to the prospective contractor; knowledge of personnel within the using or purchasing agency; commercial sources of supplier information; suppliers, subcontractors, and customers of the prospective contractor; financial institutions; government agencies; and business and trade associations.

C. Demonstration of Responsibility.

The prospective contractor may demonstrate the availability of necessary financing, equipment, facilities, expertise, and personnel by submitting upon request:

(1) evidence that such contractor possesses such necessary items;

(2) acceptable plans to subcontract for such necessary items; or

(3) a documented commitment from, or explicit arrangement with, a satisfactory source to provide the necessary items.

D. Duty Concerning Responsibility.

(1) Before awarding a contract or issuing a notification of intent to award, whichever is earlier, the procurement officer must be satisfied that the prospective contractor is responsible. The determination is not limited to circumstances existing at the time of opening.

(2) Consistent with Section 11-35-1529(3), the procurement officer must determine responsibility of bidders in competitive on-line bidding before bidding begins.

E. Written Determination of Nonresponsibility.

If a bidder or offeror who otherwise would have been awarded a contract is found nonresponsible, a written determination of nonresponsibility setting forth the basis of the finding shall be prepared by the procurement officer. A copy of the determination shall be sent promptly to the nonresponsible bidder or offeror. The final determination shall be made part of the procurement file.

F. Special Standards of Responsibility

When it is necessary for a particular acquisition or class of acquisitions, the procurement officer may develop, with the assistance of appropriate specialists, special standards of responsibility. Special standards may be particularly desirable when experience has demonstrated that unusual expertise or specialized facilities are needed for adequate contract performance. The special standards shall be set forth in the solicitation (and so identified) and shall apply to all offerors. A valid special standard of responsibility must be specific, objective and mandatory.

G. Subcontractor responsibility.

(1) Generally, prospective prime contractors are responsible for determining the responsibility of their prospective subcontractors. Determinations of prospective subcontractor responsibility may affect the procurement officer's determination of the prospective prime contractor's responsibility. A prospective contractor may be required to provide written evidence of a proposed subcontractor's responsibility.

(2) When it is in the state's interest to do so, the procurement officer may directly determine a prospective subcontractor's responsibility (e.g., when the prospective contract involves medical supplies, urgent requirements, or substantial subcontracting). In this case, the same standards used to determine a prime contractor's responsibility shall be used by the procurement officer to determine subcontractor responsibility.

Disclaimer: These regulations may not be the most recent version. South Carolina may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.