South Carolina Code of Regulations
Chapter 19 - STATE BUDGET AND CONTROL BOARD
Article 4 - OFFICE OF GENERAL SERVICES
Section 19-445.2015 - Unauthorized or Illegal Procurements
Current through Register Vol. 48, No. 9, September 27, 2024
A. Decision to Ratify or Declare Void
B. Decision to Continue or Terminate Contract. If a contract is ratified, the appropriate official must decide to either (1) continue the contract, or (2) terminate the contract and proceed as provided in section C below. A contract award or modification that is in violation of the Consolidated Procurement Code or these regulations may be continued only if the appropriate official determines an urgent and compelling need exists that cannot otherwise be met without undue burden on the State. If no such urgent and compelling need exists, the ratified contract must be terminated and the State shall proceed as provided in section C below. A contract that was ratified solely because a person lacking actual authority made an unauthorized award or modification, as described in item A(1)(a) above, does not require an urgent and compelling need to support its continuation.
C. Settlement of Terminated Contracts. If a contract is terminated as allowed by this regulation, the State shall, as appropriate and by agreement with the supplier, return any supplies delivered for a refund at no cost to the State or at a minimal restocking charge. If a contract is terminated and a termination claim is made, settlement shall be made in accordance with the contract. If there are no applicable termination provisions in the contract, settlement shall be made on the basis of actual costs directly or indirectly allocable to the contract through the time of termination. Such costs shall be established in accordance with generally accepted accounting principles. Profit shall be proportionate only to the performance completed up to the time of termination and shall be based on projected gain or loss on the contract as though performance were completed. Anticipated profits are not allowed.
D. Settlement of Void Contracts. If a contract is acknowledged as null and void pursuant to section A above, the State shall endeavor to return those supplies delivered under the contract that have not been used or distributed, and no further payments shall be made under the contract. In addition, the State is entitled to recover the greater of (1) the difference between payments made under the contract and the contractor's actual costs up until the contract was declared null and void, or (2) the difference between payments under the contract and the value to the State of the supplies, services, information technology, or construction it obtained under the contract.
E. Bad Faith. Notwithstanding section D above, the State is entitled to recover all amounts paid if the appropriate official determines that the recipient of the contract acted in bad faith. Bad faith shall not be assumed. Without limitation, specific findings showing deception, dishonesty, reckless disregard of clearly applicable laws or regulations, or deliberate breach of contract scope limits, support a finding of bad faith.
F. State's Remedies Not Limited. Regardless of its ratification of a contract, the State shall be entitled to any damages it can prove under any theory including but not limited to contract and tort.
G. Appropriate Official. The appropriate official to make the decisions authorized by sections A, B, and E above, or the determination addressed in item H(2) below, is the chief procurement officer, the head of a purchasing agency, or, for a contract with a total potential value no greater than $100,000, a designee of either officer, above the level of the person responsible for the person committing or authorizing the act. If a contract award or modification is made in violation of the Consolidated Procurement Code or these regulations, and the value of the contract exceeds the certification of the purchasing agency or one hundred thousand dollars, the chief procurement officer must concur in the written determination before any further action is taken, unless the contract is declared null and void. In all circumstances, the chief procurement officer must concur in any determination finding bad faith.
H. Determinations.
I. Reporting. Every quarter, each governmental body shall submit to the Materials Management Officer a record listing all contract awards or modifications discovered as described in item A(1) above, along with copies of the applicable written determinations. The Materials Management Officer shall submit a copy of the record to the board on an annual basis and such record shall be available for public inspection.
J. Miscellaneous.