South Carolina Code of Regulations
Chapter 103 - PUBLIC SERVICE COMMISSION
Article 5 - SEWERAGE UTILITIES
Subarticle 5 - ENGINEERING
Section 103-553 - Adequacy of Sewerage Plant

Universal Citation: SC Code Regs 103-553

Current through Register Vol. 48, No. 3, March 22, 2024

The capacity of the utility's plant for the collection, transmission, treatment and disposal of sewage, sewage effluent and other removed substances must be sufficiently large to meet all normal demands for service and provide a reasonable reserve for emergencies.

The utility shall furnish the ORS with the following:

1) Statement by the South Carolina Department of Health and Environmental Control that the design has been approved;

2) Statement by the South Carolina Department of Health and Environmental Control that the utility was installed according to plans and specifications;

3) Statement by a professional engineer that the utility design meets his approval and the utility was installed with the approval of a professional engineer; and

4) Copy of "as built" plans and specifications approved by a professional engineer.

Disclaimer: These regulations may not be the most recent version. South Carolina may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.