Section 810-RICR-00-00-3.13 - Filing of a Contract

Current through September 18, 2024

A. Within three (3) months from the issuance of the Commission's written Order, the Applicant and Electric Distribution Company shall file a proposed Long-Term Contract for review by the Commission.

B. If the Parties are unable to reach agreement on a Long-Term Contract within three (3) months, the Applicant and Electric Distribution Company shall jointly file with the Commission the terms upon which they can agree and the terms upon which they cannot agree and their respective positions on whether or not the terms upon which they cannot agree are appropriate for arbitration. The Commission will then determine whether or not to order arbitration.

C. Once the terms of the Long-Term Contract are finalized between the Applicant and the Electric Distribution Company, the Long-Term Contract shall be filed with the Commission for its review.

D. The Commission shall review the Long-Term Contract to determine whether or not it is in the best interests of the electric distribution customers in Rhode Island.

Disclaimer: These regulations may not be the most recent version. Rhode Island may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.