A. All fees are summative. In addition, all
fees are filing fees and are non-refundable.
1. New Residential Boating Facility
(pier/dock): one thousand five hundred dollars ($1,500.00)
2. Modification of under fifty percent (50%)
of size (area) of a current assented residential boating facility: two hundred
fifty dollars ($250.00)
3.
Residential development projects (condominiums, subdivisions, paper
subdivisions, etc.): three thousand five hundred dollars ($3,500.00) for the
first six (6) units/lots and four hundred dollars ($400.00) for each additional
unit/lot, plus one half of one percent (0.5%) of estimated project cost (see
below) of the infrastructure (roads, drainage, etc.) of the project. For the
purposes of this determination a paper subdivision is a subdivision of a parcel
of land which involves no application for construction (roads, utilities,
dwellings, etc.), except residential development projects.
4. All units and/or lots that are part of a
Council-approved subdivision application and are within CRMC jurisdiction and
are submitted to the Council for Assent in accordance with all conditions and
stipulations of the approved subdivision application: fee shall be equal to
half of the single-family residential home application fee
5. All other projects (not identified herein,
including reviews conducted pursuant to § 20-00-1.3.3 of this Title):
a. Estimated Project Cost (EPC).
Determination of the EPC shall be based, where applicable, on the EPC accepted
by the building official subject to acceptance by the CRMC. The EPC shall
include all costs associated with site preparation (e.g., earthwork,
landscaping, etc.), sewage treatment and disposal (e.g., cost of an Onsite
Wastewater Treatment Systems (OWTS), sewer extension, sewer tie-in, etc.), and
construction costs (e.g., materials, labor, installation of all items necessary
to obtain a Certification of Occupancy, etc.). For projects where the
determination is not available, the EPC shall be provided by the applicant
subject to its acceptance by CRMC after review of the application. For an
individual homeowner project, this can be estimated based on the best
information available concerning the construction costs. Applicants for all
other types of projects shall provide documentation showing the basis on which
the EPC was determined. Where additional specificity in the documentation is
deemed necessary by CRMC staff, a written estimate by a qualified appraiser,
engineer, or architect will be supplied by the applicant.
(1) Projects with an (EPC) up to and
including five hundred dollars ($500.00) shall be assessed a twenty-five dollar
($25.00) application fee.
(2)
Projects with an (EPC) greater than five hundred dollars ($500.00) and less
than or equal to one thousand dollars ($1,000.00) shall be assessed a fifty
dollar ($50.00) application fee.
(3) Projects with an EPC greater than one
thousand dollars ($1,000.00) and less than or equal to two thousand five
hundred dollars ($2,500.00) will be assessed a one hundred dollar ($100.00)
application fee.
(4) Projects with
an EPC greater than two thousand five hundred dollars ($2,500.00) and less than
or equal to five thousand dollars ($5,000.00) will be assessed a one hundred
fifty dollar ($150.00) application fee.
(5) Projects with EPC greater than five
thousand dollars ($5,000.00) and less than or equal to ten thousand dollars
($10,000.00) will assessed a two hundred dollar ($200.00) application
fee.
(6) Projects with EPC greater
than ten thousand dollars ($10,000.00) and less than or equal to twenty-five
thousand dollars ($25,000.00) will assessed a two hundred fifty dollar
($250.00) application fee.
(7)
Projects with EPC greater than twenty-five thousand dollars ($25,000.00) and
less than or equal to fifty thousand dollars ($50,000.00) will assessed a five
hundred dollar ($500.00) application fee.
(8) Projects with EPC greater than fifty
thousand dollars ($50,000.00) and less than or equal to one hundred thousand
dollars ($100,000.00) will assessed a seven hundred fifty dollar ($750.00)
application fee.
(9) Projects with
EPC greater than one hundred thousand dollars ($100,000.00) and less than or
equal to one hundred fifty thousand dollars ($150,000.00) will assessed a one
thousand dollar ($1,000.00) application fee.
(10) Projects with EPC greater than one
hundred fifty thousand dollars ($150,000.00) and less than or equal to two
hundred thousand dollars ($200,000.00) will assessed a one thousand two hundred
fifty dollar ($1,250.00) application fee.
(11) Projects with EPC greater than two
hundred thousand dollars ($200,000.00) and less than or equal to two hundred
fifty thousand dollars ($250,000.00) will assessed a one thousand five hundred
dollar ($1,500.00) application fee.
(12) Projects with EPC greater than two
hundred fifty thousand dollars ($250,000.00) and less than or equal to three
hundred thousand dollars ($300,000.00) will assessed a one thousand seven
hundred fifty dollar ($1,750.00) application fee.
(13) Projects with EPC greater than three
hundred thousand dollars ($300,000.00) and less than or equal to three hundred
fifty thousand dollars ($350,000.00) will assessed a two thousand dollar
($2,000.00) application fee.
(14)
Projects with EPC greater than three hundred fifty thousand dollars
($350,000.00) and less than or equal to four hundred thousand dollars
($400,000.00) will assessed a two thousand two hundred fifty dollar ($2,250.00)
application fee.
(15) Projects with
EPC greater than four hundred thousand dollars ($400,000.00) and less than or
equal to four hundred fifty thousand dollars ($450,000.00) will assessed a two
thousand five hundred dollar ($2,500.00) application fee.
(16) Projects with EPC greater than four
hundred fifty thousand dollars ($450,000.00) and less than or equal to five
hundred thousand dollars ($500,000.00) will assessed a two thousand seven
hundred fifty dollar ($2,750.00) application fee.
(17) Projects with an EPC greater than five
hundred thousand dollars ($500,000.00) and less than or equal to twenty million
dollars ($20,000,000.00) will be assessed an application fee of two thousand
seven hundred fifty dollars ($2,750.00) plus one-half of one percent (0.5%) of
the EPC beyond five hundred thousand dollars ($500,000.00), to a maximum fee of
one hundred thousand two hundred and fifty dollars ($100,250.00).
(18) Projects with an EPC greater than twenty
million dollars ($20,000,000.00) will be assessed an application fee of one
hundred thousand two hundred fifty dollars ($100,250.00) plus one-fourth of one
percent (0.25%) of the EPC beyond twenty million dollars
($20,000,000.00).
6. Maintenance fees shall be assessed as
follows:
a. Projects with an EPC up to five
hundred dollars ($500.00) will be assessed a twenty dollar ($20.00) application
fee;
b. Projects with EPC greater
than five hundred dollars ($500.00) and less than or equal to one thousand
dollars ($1,000.00) will assessed a thirty-five dollar ($35.00) application
fee;
c. Projects with an EPC
greater than one thousand dollars ($1,000.00) and less than or equal to five
thousand dollars ($5,000.00) will be assessed an application fee of fifty
dollars ($50.00).
d. Projects with
EPC greater than five thousand dollars ($5,000.00) and less than or equal to
ten thousand dollars ($10,000.00) will assessed a one hundred dollar ($100.00)
application fee.
e. Projects with
an EPC greater than ten thousand dollars ($10,000.00) and less than or equal to
twenty million dollars ($20,000,000.00) will be assessed an application fee of
one hundred dollars ($100.00) plus one-half of one percent (0.5%) of the EPC
beyond ten thousand dollars ($10,000.00), to a maximum fee of one hundred
thousand fifty dollars ($100,050.00).
f. Projects with an EPC greater than twenty
million dollars ($20,000,000.00) will be assessed an application fee of one
hundred thousand fifty dollars ($100,050.00) plus one-fourth of one percent
(0.25%) of the EPC beyond twenty million dollars ($20,000,000.00).
8. Assent Renewal or Extensions:
a. Single Family Residence: seventy-five
dollars ($75.00)
b. All Others: two
hundred fifty dollars ($250.00)
9. Request for Modification of Assent shall
be assessed the following application fees:
a.
Single Family Residence where no public hearing is necessary: one hundred
dollars ($100.00)
b. All others
shall be charged the appropriate application fee or two hundred fifty dollars
($250.00) whichever is greater.
c.
CRMC permitted aquaculture operation: one hundred dollars ($100.00)
10. Beach Vehicle Permits:
a. Annual, in-State vehicle registration: one
hundred dollars ($100.00)
b.
Annual, out-of-State vehicle registration: two hundred dollars
($200.00)
11. Lightering
fee: two hundred fifty dollars ($250.00) each transfer
12. Buffer Zone Alterations and/or Management
Plans shall be assessed the following application fees based on acreage
affected:
a. When the buffer zone alteration
and/or management plan covers less than or equal to one-half (1/2) an acre:
five hundred dollars ($500.00)
b.
When the buffer zone alteration and/or management plan covers an area greater
than one-half (1/2) an acre but less than or equal to one (1) acre: six hundred
dollars ($600.00)
c. When the
buffer zone alteration and/or management plan covers an area greater than one
(1) acre but less than or equal to five (5) acres: seven hundred fifty dollars
($750.00)
d. When the buffer zone
alteration and/or management plan covers an area greater than five (5) acres:
one thousand dollars ($1,000.00)
13. Structural Shoreline Protection
Facilities shall be changed an application fee as follows:
a. New structural shoreline protection
facilities shall be charged an application fee of one thousand five hundred
dollars ($1,500.00) for the first one hundred linear feet (100') and fifteen
dollars ($15.00) per linear foot thereafter.
b. Maintenance to structural shoreline
protection facilities shall be charged an application fee in accordance with
§ 1.4.6(A)(6) of this Part above.
14. Onsite Wastewater Treatment Systems
(OWTS) shall be charged the following application fees:
a. Single family homes (alteration or
repair): eighty dollars ($80.00)
b.
All other OWTS (alteration or repair): one hundred five dollars
($105.00)
15. If a
project requires outside consultant staff or extraordinary professional
assistance, the CRMC may negotiate a special grant with the applicant to pay
the same in accordance with R.I. Gen. Laws §
46-23-8.
16. Aquaculture Renewal Fee: seventy-five
dollars ($75.00)
17. Recreational
Aquaculture Fee:
a. Initial: fifty dollars
($50.00)
b. Annual: twenty-five
dollars ($25.00)
18.
Experimental Aquaculture, Each Site: twenty-five dollars ($25.00)
19. The Executive Director, in his discretion
and with the concurrence of the Chairman, may reduce an application fee for
commercial, industrial and mixed use projects within the urban core or growth
center coastal communities of Providence, East Providence, Pawtucket, and
Newport or for projects that meet the requirements of R.I. Gen. Laws §
42-64-7
et seq.
(Mill Building and Economic Revitalization Act), where such application is
eligible for an administrative Assent and meets all applicable programmatic
goals, policies, and standards. The reduced fee shall be no less than the
estimated processing time of Council staff of a rate per hour set by the
Planning and Procedures Subcommittee (as of May 2006: five hundred dollars
($500.00) per hour). The minimum application fee shall be five thousand dollars
($5,000.00).
20. Projects that are
determined to be brownfield sites under applicable DEM Rules and Regulations
(250-RICR-140-30-2) shall be assessed an application fee of five thousand
dollars ($5,000.00).
21.
Application fees for projects which have applied for and been accepted by the
Army Corps of Engineers as non-Federal dredging applicants in conjunction with
the Federal maintenance dredging of the Providence River and Harbor, are hereby
waived. This waiver is only available during the time that the Federal
Providence River and Harbor Maintenance Dredging project is operational, and
upon completion of this Federal navigation project this provision will become
null and void. The Executive Director shall report to the Council when this
provision becomes null and void.
22. CAD Cell Disposal Fee:
a. Marinas, Boatyards, Yacht Clubs: eleven
dollars and sixty-five cents ($11.65) per cubic yard (cy)
b. Commercial Facilities: seventeen dollars
($17.00) per cy
c. Residential
Docks: twenty-five dollars ($25.00) per cy
23.
§ 20-00-1.3.3 Waiver Requests: one
thousand dollars ($1,000.00)
24.
Project reviews conducted pursuant to § 20-00-1.3.3 of this Title, which
are determined to require a Council Assent, shall pay an application fee in
accordance with § 1.4.6(A)(5) of this Part above.
25. The application fee for Coastal Hazard
Resiliency Projects, including but not limited to flood proofing, elevating
structures and other accepted methods, in association with Army Corps of
Engineers funded projects shall be waived.