Rhode Island Code of Regulations
Title 220 - Department of Administration
Chapter 30 - Purchases
Subchapter 00 - N/A
Part 8 - Contracts (220-RICR-30-00-8)
Section 220-RICR-30-00-8.11 - Selection of Methods of Construction Contracting Management

Current through September 18, 2024

A. Construction Contract Management. The intent of § 8.11 of this Part is to specifically identify alternative methods of management of construction and the criteria to be used in selecting such methods. In addition, the intent of this Rule is to clarify that the method of source selection used to award a state contract for a particular construction project shall continue to be governed by all the applicable provisions of R.I. Gen. Laws Chapter 37-2, entitled "State Purchases", also referred to as the "State Purchases Act". These provisions include but are not limited to R.I. Gen. Laws §§ 37-2-17"Methods of source selection"; 37-2-18"Competitive sealed bidding"; 37-2-19"Competitive negotiation"; 37-2-20"Negotiations after unsuccessful competitive sealed bidding"; 37-2-21"Noncompetitive procurements"; 37-2-22 "Small purchases" and 37-2-59"Professional services - Architectural, engineering, and consultant services - Committee". Provided, however, the provisions of §§ 8.11(C) and (D) of this Part shall not apply to road, bridge and heavy construction projects which are funded in whole or in part by federal funds.

B. Road, Bridge and Heavy Construction Projects. The provisions of §§ 8.11(C) and (D) of this Part shall not apply to road, bridge and heavy construction projects that are managed by the Rhode Island Department of Transportation and are funded in whole or in part by federal funds. Road, bridge and heavy construction projects are subject to the methods of management of construction contracting, including the criteria for selecting such methods, that are set forth in applicable federal law, including but not limited to 23 U.S.C. § 112(b)(i) as amended, and regulations promulgated there under.

C. Construction Contract Management Methods and Criteria. For all other construction projects not included in § 8.11(B) of this Part, the methods below, along with the criteria for each method, are the alternative methods of construction contract management deemed feasible by the Chief Purchasing Officer. The methods below are not mutually exclusive and may be combined on a project.

1. General Contractor Method. The general contractor method is typified by one business, acting as a general contractor, contracting with the State to timely complete an entire construction project in accordance with drawings and specifications provided by the State. Generally the drawings and specifications are prepared by an architectural or engineering firm under contract with the State. Further, while the general contractor may take responsibility for successful completion of the project, much of the work may be performed by specialty contractors with whom the general contractor has entered into subcontracts. The general contractor method is the generally preferred method of construction work. It may be selected for a project only when it is determined in writing by the Chief Purchasing Officer that the following criteria will be met:
a. the project requires timely completion of the construction work in accordance with drawings and/or specifications provided by the State and/or the State's agent.

b. the project work may be performed by specialty sub- contractors under the control and supervision of a general contractor.

c. the project does not require direct supervision or coordination between the contractor and project engineering/design professionals other than as normally performed by State employees.

d. the construction project is estimated to cost in excess of ten thousand dollars ($10,000).

e. sufficient time exists to complete the design, bid the project and construct the work by the desired occupancy date.

2. Multiple Prime Contractors. Under the multiple prime contractor method, the State or its agent contracts directly with any number of contractors, often representing different trades, to complete portions of the project in accordance with the State's drawings and specifications. The State and/or its agent shall have primary responsibility for successful completion of the entire project. The multiple prime contractor method may be selected for a project only when it is determined in writing by the Chief Purchasing Officer that the following criteria will be met:
a. the State or its agent is able to coordinate job site activities of any number of contractors and/or subcontractors with varying areas of construction expertise to complete portions of the project in accordance with the State's drawings and specifications, and the State or its agent will contract directly with such contractors and/or subcontractors.

b. the State and/or its agent is able to assume primary responsibility for successful completion of the entire project.

c. the construction project is for the rehabilitation or renovation of a building or buildings.

d. the contract(s) for the rehabilitation or renovation of any building(s) in the aggregate are estimated to cost less than two million dollars ($2,000,000).

3. Design-Build. In a design-build project, a person or firm contracts directly with the State to meet the State's requirements as described in a set of design or engineering specifications, bridging documents, or scope of work. Final design and construction are both the responsibility of the design-build contractor. This method can include projects where the design-build contractor supplies the site as part of the design-build package. The design-build method may be selected for a project only when it is determined in writing by the Chief Purchasing Officer that the following criteria will be met:
a. the State does not have the ability to prepare the requisite design or engineering specifications, bridging documents, or scope of work.

b. the State cannot manage or supervise the work of specialty trade contractors and it is not in the State's best interest to contract directly with such specialty contractors.

c. the State determines that it is in its best interest for a design- build firm to assume responsibility for both final design and construction of the project.

d. due to time constraints and the need to complete the project on an expedited basis, it is in the State's best interest to select a design-build contractor rather than a general contractor for the project.

e. construction work on the project has an estimated cost equal to or greater than two-million five-hundred thousand dollars ($2,500,000).

f. the State desires to have a single firm responsible for both design and construction.

4. Construction Manager At Risk. The terms "Construction Manager at Risk", "construction management at-risk services," "construction management at-risk delivery method" shall all be limited to that certain construction method defined by R.I. Gen. Laws § 37-2-7(30). The terms "construction manager at-risk" and "construction management at-risk firm" shall be limited as defined by R.I. Gen. Laws § 37-2-7(31). The construction manager at risk method of construction management may be selected for a project only when it is determined in writing by the Chief Purchasing Officer that all criteria mandated by R.I. Gen. Laws §§ 37-2-27.2, 27.3, and 27.4, as amended have been met.

5. "Owner's Program Manager" shall be limited to that certain construction method defined by R.I. Gen. Laws § 37-2-7(32), as amended. The Owner's Program Manager method may be selected for a project only when it is determined in writing by the Chief Purchasing Officer that the following criteria will be met:
a. the State does not have the ability to prepare the requisite design or engineering specifications, bridging documents, or scope of work;

b. the State cannot manage or supervise the work of specialty trade contractors and will not contract directly with such specialty trade contractors;

c. it is in the State's best interest to retain a program manager to supervise and or monitor the activities of a general contractor; and/or

d. it is in the State's best interest to retain a program manager to supervise and or monitor the engineering and architectural services for a project;

e. the construction project has an estimated cost equal to or greater than ten thousand dollars ($10,000).

D. Construction Contract Management Selection Information. In addition to criteria set-forth in § 8.11(C) of this Part, the following information for a particular project shall be submitted to the Chief Purchasing Officer under § 8.11(E) of this Part:

1. when the project must be completed or ready for occupancy or use;

2. the specific nature of the project and its specialized needs, e.g. housing, offices, laboratories, and specialized construction;

3. the extent to which the requirements of the procuring agency and the ways in which said requirements are to be met are known;

4. the location of the project;

5. the size, scope, complexity, and economics of the project;

6. the amount and type of financing available for the project, including whether the budget is fixed and the source of funding, e.g., general or special appropriation, federal assistance moneys, general obligation bonds or revenue bonds;

7. the availability, qualification, and experience of State personnel to be assigned to the project and how much time the State personnel can devote to the project;

8. the availability, experience and qualifications of outside consultants and contractors to complete the project under the various methods being considered;

9. the method of source selection under the State Purchases Act that will be used to award a contract to a vendor for this particular project.

E. Documentation of Selection Determination. Using and including the information in § 8.11(D) of this Part, the purchasing agent or purchasing agency responsible for carrying out the construction project shall set forth in writing to the Chief Purchasing Officer the facts that led to the selection of a particular method of construction contract management pursuant to the criteria set forth in §§ 8.11(B) or (C) of this Part and the information required in § 8.11(D) of this Part. The Chief Purchasing Officer shall include in the contract file a written statement setting forth the facts that led to the selection of a particular method of management of construction in each instance. The Chief Purchasing Officer's written statement may adopt, in whole or in part, any written statements provided by the purchasing agent or the purchasing agency.

F. Protest. Any actual or prospective bidder, offeror, or contractor, who is aggrieved in connection with the solicitation, selection, or award of a method of construction management contract, may file a bid protest with the Chief Purchasing Officer pursuant to R.I. Gen Laws § 37-2-52 using the procedures required by § 1.6 of this Subchapter.

Disclaimer: These regulations may not be the most recent version. Rhode Island may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.