Rhode Island Code of Regulations
Title 220 - Department of Administration
Chapter 30 - Purchases
Subchapter 00 - N/A
Part 6 - Negotiation
Section 220-RICR-30-00-6.6 - Subcontracting - Requirements
Current through September 18, 2024
A. Prime contractors shall require subcontractors to submit cost or pricing data for procurements in excess of fifty thousand dollars ($50,000.00) unless exempted herein.
B. Certification - Prime contractors shall require subcontractors to certify that cost and pricing data submitted are accurate, complete, and current as of the date of agreement on price.
C. Under R.I. Gen. Laws § 37-2-28(b), any contract, change, or modification thereto under which a certificate is required shall contain a provision that the price to the State, including profit or fee, shall be adjusted to exclude any significant sums by which the Purchasing Agent finds that such price was increased because the contractor furnished cost or pricing data, as of the date agreed upon between the parties, was inaccurate, incomplete, or not current.
D. Prime contractors must agree that the prime contract price shall be reduced in any significant amounts by which the prime contract price was overstated because a subcontractor did not submit accurate, complete, and current cost or pricing data when required by law.