Current through September 18, 2024
1.14.1
Applicability
Any Asbestos Contractor that engages in any Asbestos
Abatement Project that involves greater than ten (10) linear feet (three (3)
meters) of pipe covered or coated with asbestos containing material or twenty
five (25) square feet (three (3) square meters) of asbestos containing material
used to cover or coat any surface other than pipe shall comply with the work
practices contained in §
1.14 of this Part and any
additional work practice requirements contained in the asbestos abatement plan
approved for that project by the Director of Health. Specific requirements for
Category I and Category II Nonfriable ACM that is not Regulated Asbestos
Containing Material (RACM) are contained in §§ 1.14.8 and 1.15 of
this Part.
1.14.2
General Requirements for Removal, Encapsulation and/or Enclosure of
Regulated Asbestos Containing Material (RACM)
A. Barriers to isolate contaminated from
uncontaminated areas shall be constructed of polyethylene sheeting attached
securely in place.
B. All surfaces
shall be wet cleaned of dust or debris. Wet cleaning of contaminated items
shall be performed if necessary. All movable objects shall be removed from the
work area. All nonmovable objects in the work area shall be covered with 6-mil
polyethylene sheeting secured in place. All openings or penetrations between
the work area and uncontaminated areas shall be sealed, including windows,
doorways, elevator openings, corridor entrances, drains, ducts, grills, grates,
diffusers and skylights.
C. Floor
sheeting shall consist of two (2) layers of 6-mil polyethylene sheeting. Floor
sheeting shall extend up sidewalls at least twelve (12) inches and be sized to
minimize seams. No seams shall be located at wall/floor joints. Floors being
abated of resilient floor coverings and associated mastics/adhesives shall be
exempt from this requirement.
D.
Wall sheeting shall consist of two (2) layers of 4-mil polyethylene sheeting.
It shall be installed to minimize joints and shall extend beyond wall/floor
joint at least twelve (12) inches. No seams shall be located at wall/wall
joints.
E. A worker decontamination
enclosure system, consisting of a clean room, shower room and equipment room,
each separated from each other and from the work area by airlocks and
accessible through doorways protected with two (2) overlapping polyethylene
sheets, shall be provided in accordance with OSHA
29 C.F.R. §
1926.1101(j) incorporated by
reference at §
1.2(A) of
this Part. Procedures for the utilization of this system shall be established
which prevent contamination of areas outside the work area.
F. All HVAC equipment in or passing through
the work area shall be shut down and locked out. All intake and exhaust
openings, as well as any seams in system components shall be sealed with 6-mil
polyethylene sheeting and/or tape. All system filters shall be replaced after
the abatement and disposed of as asbestos waste. The ventilation system
ductwork interiors shall be decontaminated whenever necessary.
G. Posting
1. Warning signs in accordance with OSHA
29 C.F.R. §
1926.1101(k)(7) incorporated
by reference at §
1.2(A) of
this Part shall be displayed at all approaches to any location where airborne
fiber levels can be expected to exceed the Indoor Non-Occupational Air Exposure
Standard established by §
1.5 of this Part.
2. Warning signs to advise the public of the
location(s) within the building where any asbestos abatement activity is in
progress shall be posted at all building entrances and at least one other
conspicuous place per floor. These signs shall be of the same dimensions as the
Warning/Danger signs required in § 1.14.2(G)(1) of this Part.
3. Warning signs shall be posted on vehicles
used to transport Asbestos Containing Waste Materials during loading and
unloading of the waste.
H. Clean-up procedures using HEPA vacuuming
and wet cleaning techniques shall be performed following abatement. Wet
cleaning shall be followed by HEPA vacuuming after surfaces have been allowed
to dry. The sequence of wet cleaning and vacuuming shall be repeated at
twenty-four (24) hour intervals until no visible residue is observed in the
work area.
I. Negative pressure
ventilation units with HEPA filtration, in sufficient number to provide one (1)
workplace air change every fifteen (15) minutes, shall be operated continuously
from the time of barrier construction through the time acceptable final
clearance air-monitoring results are obtained. These units shall exhaust
filtered air to the outside of the building. Filtered air shall not be
exhausted to uncontaminated interior spaces.
J. All Asbestos Containing Waste Materials
shall be adequately wetted before being placed into containers for
disposal.
K. Asbestos Containing
Waste Materials shall be placed in impermeable containers for disposal. Metal
or fiber drums with locking-ring tops shall be used when asbestos waste
contains sharp edged components. Double polyethylene bags of at least 6-mil
thickness and which can be securely sealed may be used for waste. Large
components or structural members may be removed intact and contained in
leak-tight wrapping, equivalent to at least two (2) layers of 6-mil
polyethylene sheeting, secured with tape for disposal.
L. All containers, bags, drums and wrapped
components shall be labeled so that labels have the appearance of or are
constructed in accordance with USDOT 49 C.F.R. 172, Subpart E incorporated by
reference at §
1.2(D) of
this Part and OSHA 29 C.F.R.
§
1926.1101(k)(8)
incorporated by reference at §
1.2(A) of
this Part. Each container, bag, drum or wrapped component shall also be labeled
or tagged with the name and license number of the asbestos contractor
generating the waste, as well as the asbestos abatement project number and
location at which the waste was generated.
M. Storage of asbestos waste containers
awaiting transport to an authorized disposal facility shall be in a secured
location to prevent access by unauthorized personnel.
N. Transport and disposal of asbestos waste
shall be in accordance with the provisions of Appendix D to 40 C.F.R. 763,
Subpart E incorporated by reference at §
1.2(E) of
this Part and USDOT 49 C.F.R. § 173.1300 incorporated by reference at
§
1.2(F) of
this Part.
O. Disposal of Asbestos
Containing Waste Materials. All Asbestos Containing Waste Materials shall be
deposited as soon as is practical by the waste generator at:
1. A waste disposal site operated in
accordance with the provisions of
40 C.F.R. §
61.154, or equivalent regulations promulgated
by a state or local NESHAP designee; or
2. An EPA-approved site that converts RACM
and Asbestos Containing Waste Materials into nonasbestos (asbestos-free)
material according to the provisions of
40 C.F.R. §
61.155.
P. Access to work areas shall be controlled
and posting requirements shall remain in effect until compliance with the air
exposure standard has been verified by procedures outlined below:
1. Samples shall be collected and analyzed in
accordance with the procedures specified by NIOSH Method 7400 (most current
Revision) for asbestos fibers in air or equivalent method;
2. Air volumes shall be sufficient to
accurately determine fiber concentrations to 0.01 fibers/ cubic centimeter of
air (f/cc) for fibers greater than five (5) microns in length or 300 nanograms
per cubic meter. A minimum air volume of 1000 liters shall be
sampled;
3. Air sampling shall be
conducted in representative locations with portable fans circulating air to
simulate actual use conditions;
4.
An acceptable airborne fiber concentration, as established by clearance air
monitoring shall not exceed 0.01 f/cc for fibers greater than five (5) microns
in length or 300 nanograms per cubic meter; and
5. Air sampling shall be conducted by a
representative of the building owner who is not subject to the control or
supervision of the Asbestos Contractor for the asbestos abatement
plan.
6. Notwithstanding the
requirements contained in § 1.14.2(P) of this Part above, control of
access and posting requirements for buildings subject to the AHERA regulations
shall remain in effect until compliance with §§1.17.3(A)(5) through
(8) of this Part has been demonstrated.
1.14.3
Specific Requirements for
Removal of Regulated Asbestos Containing Material (RACM)
A. All RACM shall be adequately wetted prior
to removal. In addition, all RACM exposed during cutting and disjoining
operations shall be adequately wet and all RACM shall be kept adequately wet
during stripping operations.
B.
Components shall be removed intact or in large sections whenever possible and
carefully lowered to the floor.
C.
RACM shall be removed in small sections and containerized when adequately wet.
At no time shall material be allowed to accumulate or become dry. Structural
components shall be adequately wetted prior to being contained in leak-tight
wrapping for disposal.
D. Material
shall not be dropped or thrown to the floor level. For materials located at
heights greater than fifty (50) feet above the floor, a dust-tight, enclosed
chute shall be constructed to transport removed material to containers on the
floor. RACM may be dropped to a raised scaffold or containerized at elevated
levels for disposal. Materials greater than fifteen (15) feet above the floor
shall be dropped onto inclined chutes or scaffolding or containerized at
elevated levels for eventual disposal.
E. A coating of encapsulating agent shall be
applied to any porous surfaces that have been stripped of RACM to securely seal
any residual fibers that may be present. The encapsulating agent should be
chosen to be compatible with subsequent coverings.
F. RACM is not required to be stripped from
large facility components such as reactor vessels, large tanks, and steam
generators if the following requirements are met:
1. The component is removed, transported,
stored, disposed of, or reused without disturbing or damaging the
RACM.
2. The component is encased
in a leak-tight wrapping.
3. The
leak-tight wrapping is labeled during all loading and unloading operations and
during storage.
G. When
the temperature at the point of wetting is below 0°C (32°F):
1. The Asbestos Contractor need not comply
with the wetting provisions of §§ 1.14.3(A) and (C) of this
Part.
2. The Asbestos Contractor
shall remove facility components containing, coated with, or covered with RACM
as units or in sections to the maximum extent possible.
3. During periods when wetting operations are
suspended due to freezing temperatures, the Asbestos Contractor must record the
temperature in the area containing the facility components at the beginning,
middle, and end of each workday and keep daily temperature records available
for inspection by the Department during normal business hours at the asbestos
abatement project site. The Asbestos Contractor shall retain temperature
records for at least two years.
1.14.4
Specific Requirements for
Encapsulation of Regulated Asbestos Containing Material (RACM)
A. All loose and hanging RACM shall be
removed in accordance with § 1.14.3 of this Part.
B. Filler material applied to gaps in
existing material shall contain no asbestos, adhere well to the substrate and
provide an adequate base for the encapsulating agent.
C. Encapsulants shall be applied using only
airless spray equipment with nozzle pressure adjustable between four hundred
(400) and fifteen hundred (1500) PSI and in accordance with the manufacturer's
recommendations for a particular encapsulant.
D. Encapsulated materials shall be specially
designated by signs, labels, color coding or some mechanism to warn individuals
who may be required to disturb the material.
E. Encapsulants shall not be solvent-based or
utilize a vehicle consisting of hydrocarbons.
1.14.5
Specific Requirements for
Enclosure of Regulated Asbestos Containing Material (RACM)
A. All areas of RACM shall be adequately
wetted with wetting agents if they are to be disturbed during the installation
of hangers, brackets or other portions of the enclosure.
B. All loose and hanging RACM shall be
removed in accordance with § 1.14.3 of this Part.
C. Non-asbestos containing substitutes shall
be used to patch thermal insulation and fireproofing materials when required
and where appropriate.
D.
Enclosures for RACM shall be specially designated by signs, labels, color
coding or some mechanism to warn individuals who may be required to disturb or
enter the enclosure.
1.14.6
Specific Requirements for
Demolition of Structures Containing Asbestos
A. Any demolition of a structure or portion
of a structure which contains structural members, building materials or
structural components composed of or covered by RACM shall be preceded by a
removal of all such materials in accordance with §§ 1.14.2 and 1.14.3
of this Part. Said removal must be completed before any activity begins that
would break up, dislodge, or similarly disturb the material or preclude access
to the material for subsequent removal. Notwithstanding the foregoing, RACM
need not be removed before demolition if:
1.
It is Category I nonfriable ACM that is not in poor condition and is not
friable; or
2. It is on a facility
component that is encased in concrete or other similarly hard material and is
adequately wet whenever exposed during demolition; or
3. It was not accessible for testing and was,
therefore, not discovered until after demolition began and, because of the
demolition, the material cannot be safely removed. If not removed for safety
reasons, the exposed RACM and any asbestos contaminated debris must be treated
as Asbestos Containing Waste Material and adequately wet at all times until
disposed of; or
4. It is Category
II nonfriable ACM and the probability is low that the materials will become
crumbled, pulverized, or reduced to powder during demolition.
B. For Emergency Asbestos
Abatement Projects described in §1.6.2(C) of this Part, adequately wet the
portion of the facility that contains RACM during the wrecking
operation.
C. If a facility is
demolished by intentional burning, all RACM, including Category I and Category
II nonfriable ACM, must be removed in accordance with this Part before
burning.
D. In lieu of the
requirements specified in §§1.14.2(B), (C), (D), (F) and 1.14.3(E) of
this Part, Asbestos Contractors engaging in demolition activities shall comply
with the following:
1. Prior to beginning a
demolition project, all doors, windows, floor drains, vents and other openings
to the outside of the building and to areas within the building that do not
contain asbestos materials shall be sealed off with 6-mil polyethylene sheeting
and waterproof tape or equivalent acceptable to the Department.
2. If a structure is to be partially
demolished, HVAC equipment in the demolition area or passing through it but
servicing areas of the building which will remain, shall be shut down and
locked out and thoroughly sealed with 6-mil polyethylene sheeting and
waterproof tape.
3. If the building
owner proposes not to conduct clearance air sampling following asbestos
abatement activities conducted for demolition purposes, the building owner must
submit written justification to the Department which describes how personnel
who must occupy the building prior to demolition will be protected.
4. All other requirements of
§§1.14.2 and 1.14.3 of this Part, unless specified in §1.14.6(D)
of this Part, shall apply to demolition abatement
activities.
1.14.7
General Requirements for Use of
Glove Bags During Removal and/or Encapsulation of Regulated Asbestos Containing
Material (RACM)
A. In lieu of the
requirements specified in §§1.14.2(A) through (F), (H), and (I) of
this Part, Asbestos Contractors using glove bags during removal and/or
encapsulation of RACM shall comply with the following:
1. All glove bags must remain stationary
during asbestos abatement activities. The use of moving and/or sliding glove
bag techniques are prohibited.
2.
Abatement projects which do not exceed the scope of Spot Repairs, as defined by
this Part, and which can be contained within one stationary glove bag may be
performed in accordance with the glove bag procedures contained in
29 C.F.R. §
1926.1101(g)(5) incorporated
by reference at §
1.2(A) of
this Part without the use of additional containment or negative pressure
ventilation. The clearance air monitoring provisions of §1.14.2(P) of this
Part are waived unless there has been a breach of the glove bag
containment.
3. All other abatement
projects that involve less than two hundred and sixty (260) linear feet [eighty
(80) meters] of pipe covered or coated with RACM or one hundred and sixty (160)
square feet [fifteen (15) square meters] of RACM used to cover or coat any
surface other than pipe shall comply with the following requirements:
a. All doors, windows, floor drains, vents
and other openings to the outside of the building and to areas within the
building that do not contain asbestos materials shall be sealed off with 6-mil
polyethylene sheeting and waterproof tape or equivalent acceptable to the
Department.
b. Floor sheeting shall
consist of at least one (1) layer of 6-mil polyethylene sheeting. Floor
sheeting shall be placed directly beneath the glove bag and shall extend at
least ten (10) feet in all horizontal directions. If any wall is less than ten
(10) feet from the glove bag, the floor sheeting shall be extended up that wall
to at least the height of the glove bag.
c. HVAC equipment in the abatement area or
passing through it but servicing other areas of the building shall be shut down
and locked out and thoroughly sealed with 6-mil polyethylene sheeting and
waterproof tape.
d. Negative
pressure ventilation units with HEPA filtration shall be operated continuously
from the time of barrier construction through the time acceptable final
clearance air-monitoring results are obtained. These units shall exhaust
filtered air to the outside of the building. Filtered air shall not be
exhausted to uncontaminated interior spaces.
e. Manufacturer's instructions concerning
preparation, sealing, utilization and removal of glove bags must be followed
unless the abatement plan and/or this Part specify more restrictive
requirements.
f. A worker
decontamination enclosure system must be available immediately adjacent to the
abatement area. A two-chamber decontamination system may be used if shower
facilities are otherwise available on the project site.
4. All abatement projects that involve more
than two hundred and sixty (260) linear feet [eighty (80) meters] of pipe
covered or coated with RACM or one hundred and sixty (160) square feet [fifteen
(15) square meters] of RACM used to cover or coat any surface other than pipe
shall comply with the following requirements:
a. All doors, windows, floor drains, vents
and other openings to the outside of the building and to areas within the
building that do not contain asbestos materials shall be sealed off with 6-mil
polyethylene sheeting and waterproof tape or equivalent acceptable to the
Department.
b. Floor sheeting shall
consist of at least one (1) layer of 6-mil polyethylene sheeting. Floor
sheeting shall extend up sidewalls at least twelve (12) inches and be sized to
minimize seams. No seams shall be located at wall/floor joints.
c. Wall sheeting shall consist of at least
one (1) layer of 4-mil polyethylene sheeting. It shall be installed to minimize
joints and shall extend from the wall/ ceiling joint to at least twelve (12)
inches beyond the wall/floor joint. No seams shall be located at wall/wall
joints.
d. HVAC equipment in the
abatement area or passing through it but servicing other areas of the building
shall be shut down and locked out and thoroughly sealed with 6-mil polyethylene
sheeting and waterproof tape.
e.
Negative pressure ventilation units with HEPA filtration shall be operated
continuously from the time of barrier construction through the time acceptable
final clearance air monitoring results are obtained. These units shall exhaust
filtered air to the outside of the building. Filtered air shall not be
exhausted to uncontaminated interior spaces.
f. Manufacturer's instructions concerning
preparation, sealing, utilization and removal of glove bags must be followed
unless the abatement plan and/or this Part specify more restrictive
requirements.
g. A three-chamber
worker decontamination enclosure system, in accordance with
29 C.F.R. §
1926.1101(j) incorporated by
reference at §
1.2(A) of
this Part, must be available immediately adjacent to the abatement
area.
5. All other
requirements of §§1.14.2 and 1.14.3 of this Part, unless specifically
deleted in §1.14.7(A) of this Part, shall apply to use of glove bags
during removal and/or encapsulation of asbestos.
B. Any requests for additional waivers and/or
alternative procedures must be submitted for Department review and approval in
accordance with §
1.16 of this
Part.
1.14.8
Specific Requirements for Removal of Category I Nonfriable ACM - Asphalt
Roofing Products
A. All surfaces shall
be wet cleaned of dust or debris. All movable objects shall be removed from the
roof area. All openings or penetrations on the roof area and at least one level
below the roof area shall be sealed, including windows, doorways, drains,
ducts, grills, grates, diffusers and skylights.
B. Floor/ground sheeting shall consist of at
least two (2) layers of 6-mil polyethylene sheeting and shall be utilized as
follows:
1. If the roof is pitched, sheeting
shall be applied to the first horizontal surface below the work area and shall
extend from the edge of the building to at least ten (10) feet away from the
building. All material being abated shall be confined to the roof
area.
2. If the roof is flat,
sheeting shall extend at least ten (10) feet away from the perimeter of the
work area. When the edge of the roof is less than ten (10) feet from the
perimeter of the work area, sheeting shall be applied such that the outer edge
of the sheeting is at least ten (10) feet from the perimeter of the work
area.
C. All HVAC intake
or exhaust vents on the roof area and at least one level below the roof area
shall be shut down and locked out. All intake and exhaust openings, as well as
any seams in system components shall be sealed with 6-mil polyethylene sheeting
and/or tape.
D. A minimum of a
two-chambered worker decontamination enclosure system shall be provided on
site. Procedures for the utilization of this system shall be established which
prevent contamination of areas outside the roof area.
E. Warning signs shall be posted in
accordance with §1.14.2(G) of this Part.
F. Category I Nonfriable ACM shall be removed
in small sections and containerized when wet. At no time shall material be
allowed to accumulate or become dry.
G. Category I Nonfriable ACM shall not be
dropped or thrown to the floor/ground level. For roofs at heights greater than
fifty (50) feet above the floor/ground, a dust-tight, enclosed chute shall be
constructed to transport removed Category I Nonfriable ACM to containers on the
floor/ground. Category I Nonfriable ACM may be dropped to a raised scaffold or
containerized at elevated levels for disposal.
H. All Category I Nonfriable ACM shall be
adequately wetted before being placed into containers for disposal. Disposal
shall be in accordance with §§1.14.2(K) through (O) of this
Part.
I. A coating of encapsulating
agent shall be applied to any porous surfaces that have been stripped of
Category I Nonfriable ACM to securely seal any residual fibers that may be
present. The encapsulating agent should be chosen to be compatible with
subsequent coverings.
J. Clean-up
procedures using HEPA vacuuming and wet cleaning techniques shall be performed
following abatement.
K. Personnel
air monitoring of Asbestos Supervisors and Asbestos Workers, which demonstrates
compliance with the provisions of OSHA
29 C.F.R. §
1926.1101(f) incorporated by
reference at §
1.2(A) of
this Part, may be used in lieu of the clearance air sampling requirements
contained in §1.14.2(P) of this Part.