Current through Register Vol. 54, No. 38, September 21, 2024
(a) Purpose. The Commission will establish a pole attachment working group to ensure that the Commission remains apprised of industry concerns, that Federal amendments are properly vetted before becoming effective in this Commonwealth and that dispute resolution processes are efficient and effective.
(b) Creation of Working Group. The Commission's Law Bureau will establish the Working Group, in coordination with the Commission's Bureau of Technical Utility Services and the Office of Special Assistants, no later than 30 days from the effective date of this chapter.
(c) Membership. The Commission will invite persons and entities that it determines to be in the public interest to participate in the Working Group including, but not limited to, the following:
(d) Meeting Frequency. The Working Group shall convene at least once annually but may convene at other times, as the Working Group deems necessary or at the direction of the Commission.
(e) Duties. The Working Group shall:
(f) Reporting. The Law Bureau will annually report its findings on issues developed in the pole attachment Working Group along with any recommended Commission action as appropriate.