(a) This chapter establishes the Commission's regulatory authority over the rates, terms and conditions of access to and use of utility poles, ducts, conduits and rights-of-way to the full extent of this Commission's jurisdiction and authority and as provided for in 47 U.S.C. § 224 for pole attachments but excluding any person or entity expressly exempted by 47 U.S.C. § 224(a)(1) and 47 CFR 1.1402(a) (relating to definitions) as of 60 days after the effective date of this chapter.
(b) The Commission has the authority to consider the interests of the subscribers of the services offered by means of pole attachments, as well as the interests of the consumers of the utility services.