Current through Register Vol. 54, No. 38, September 21, 2024
(a) An EDC shall use the Level 1
interconnection review procedure for an interconnection request that meets the
criteria in §
75.34(1)
(relating to review procedures). An EDC may not impose additional requirements
for Level 1 reviews not specifically authorized under this
subchapter.
(b) The Level 1
screening criteria must consist of:
(1) For
interconnection of a proposed small generator facility to a radial distribution
circuit, the aggregated generation on the circuit, including the proposed small
generator facility, may not exceed 15% of the line section annual peak load as
most recently measured at the sub station.
(2) For interconnection of a proposed small
generator facility to the load side of spot network protectors, the proposed
small generator facility shall utilize an inverter-based equipment package. The
customer interconnection equipment proposed for the small generator facility
must be certified, and when aggregated with other generation, may not exceed 5%
of the spot network's maximum load.
(3) When a proposed small generator facility
is to be interconnected on a single-phase shared secondary line, the aggregate
generation capacity on the shared secondary line, including the proposed small
generator facility, may not exceed 20 kW.
(4) When a proposed small generator facility
is single-phase and is to be interconnected on a center tap neutral of a 240
volt service, its addition may not create an imbalance between the two sides of
the 240 volt service of more than 20% of the nameplate rating of the service
transformer.
(5) Construction of
facilities by the EDC on its own system is not required to accommodate the
small generator facility.
(c) The Level 1 interconnection review
procedure must consist of:
(1) An EDC shall,
within 10 business days after receipt of the interconnection request, inform
the applicant that the interconnection request is complete or incomplete and
what materials are missing.
(2) The
EDC shall, within 15 business days after the end of the 10 business days noted
in paragraph (1), verify that the small generator facility equipment can be
interconnected safely and reliably using Level 1 screens. When an EDC does not
have a record of receipt of the interconnection request, and the applicant can
demonstrate that the original interconnection request was delivered, the EDC
shall expedite its review to complete the evaluation of the interconnection
request within 15 days of the applicant's resubmittal.
(3) Upon notice, within 10 business days
after receipt of the certificate of completion, an EDC may conduct a witness
test at a mutually convenient time. If the EDC does not conduct the witness
test within 10 business days or within the time otherwise mutually agreed to by
the parties, the witness test is deemed waived.
(4) Unless an EDC determines and demonstrates
that a small generator facility cannot be interconnected safely and reliably,
the EDC shall approve the interconnection request form subject to the following
conditions:
(i) The small generator facility
has been approved by local or municipal electric code officials with
jurisdiction over the interconnection.
(ii) A certificate of completion has been
returned to the EDC. Completion of local inspections may be designated on
inspection forms used by local inspecting authorities.
(iii) The witness test has been successfully
completed or waived.
(iv) The
interconnection customer has signed a standard small generator interconnection
agreement. When an interconnection customer does not sign the agreement within
30 business days after receipt from the EDC, the interconnection request will
be deemed withdrawn unless the interconnection customer requests to have the
deadline extended. The request for extension may not be unreasonably denied by
the EDC.
(5) When a small
generator facility is not approved under a Level 1 review, the interconnection
customer may submit a new interconnection request for consideration under Level
2, Level 3 or Level 4 procedures specified in this chapter without sacrificing
the applicant's original queue position.
This section cited in 52 Pa. Code §
69.2101 (relating to statement of
scope); 52 Pa. Code §
69.2102 (relating to statement of
purpose); 52 Pa. Code §
69.2103 (relating to definitions);
and 52 Pa. Code §
69.2104 (relating to
interconnection application fees).