Pennsylvania Code
Title 52 - PUBLIC UTILITIES
Part I - Public Utility Commission
Subpart C - Fixed Service Utilities
Chapter 75 - ALTERNATIVE ENERGY PORTFOLIO STANDARDS
Subchapter C - INTERCONNECTION STANDARDS
INTERCONNECTION PROVISIONS
Section 75.34 - Review procedures
Current through Register Vol. 54, No. 38, September 21, 2024
An EDC shall review interconnection requests using one or more of the following four review procedures:
(1) An EDC shall use Level 1 procedures for evaluation of all interconnection requests to connect inverter-based small generation facilities when:
(2) An EDC shall use Level 2 procedures for evaluating interconnection requests to connect small generation facilities when:
(3) An EDC shall use Level 3 review procedures for evaluating interconnection requests to connect small generation facilities with an electric nameplate capacity of 2 MW or less which do not qualify under Level 1 or Level 2 interconnection review procedures or which have been reviewed under Level 1 or Level 2 review procedures, but have not been approved for interconnection.
(4) Interconnection customers that do not qualify for Level 1 or Level 2 review and do not export power beyond the point of common coupling may request to be evaluated under Level 4 review procedures which provide for a potentially expedited review process.
This section cited in 52 Pa. Code § 69.2101 (relating to statement of scope); 52 Pa. Code § 69.2102 (relating to statement of purpose); 52 Pa. Code § 69.2104 (relating to interconnection application fees); and 52 Pa. Code § 75.37 (relating to level 1 interconnection review); and 52 Pa. Code § 75.38 (relating to review procedures).