(a) A public utility which intends to file a general rate increase request of $1 million or more should provide by letter and certificate of service 30 days advance notice of the rate filing to the following:
(b) The advance notice should contain a reasonable estimate of the amount to be sought, a brief outline of the major reasons for the increase-for example, major plant addition, significant increase in particular expenses and the like-and an identification of other major issues in the case.
(c) Within 20 days in advance of the anticipated general rate increase filing, the OSA will send to the customary parties a notice indicating that they should begin preparation of discovery, engage a consultant, if necessary, and assemble a team of attorneys and technicians to litigate the case.
This section cited in 52 Pa. Code § 69.401 (relating to general).