Pennsylvania Code
Title 52 - PUBLIC UTILITIES
Part I - Public Utility Commission
Subpart C - Fixed Service Utilities
Chapter 69 - GENERAL ORDERS, POLICY STATEMENTS AND GUIDELINES ON FIXED UTILITIES
SAFETY AND RELIABILITY GUIDELINES
Section 69.15 - Ensuring sufficient firm capacity availability
Current through Register Vol. 54, No. 38, September 21, 2024
(a) NGSs using firm gas supply contracts with Pennsylvania producers or storage or transportation capacity contracts acquired through assignment or release by NGDCs or acquired as the result of the nonrenewal of a storage or transportation capacity contract previously held by the NGDC should offer the SOLR, or the successor NGS, a right of first refusal to utilize the contracts at the NGS's contract cost as long as needed to serve retail gas customers being relinquished by the NGS.
(b) NGSs using storage or transportation capacity contracts acquired in a manner other than through assignment, release or nonrenewal by the NGDC should provide the SOLR a right of first refusal to use the capacity at contract cost if the NGS failed to give the SOLR and the NGDC sufficient notice or if there is insufficient alternative capacity available to serve the market being relinquished by the NGS.
This section cited in 52 Pa. Code § 69.11 (relating to definitions); and 52 Pa. Code § 69.19 (relating to operational and capacity councils).