Section 69.3102 - Public notice filing requirements
Current through Register Vol. 54, No. 38, September 21, 2024
(a) Applications for electric transmission siting authority should provide the following information with the initial application for siting approval demonstrating its efforts to fully notify landowners who are either owners of land that will be purchased for the transmission project or will be subject to right of way/easement requirements:
(b) Applicants for transmission siting authority should serve a copy of the Code of Conduct on all landowners along the proposed route whose property is to be purchased, subject to easement rights or borders the transmission corridor. The Code of Conduct should also be available on the applicant's website.
(c) Applicants for transmission siting authority should provide prior notice to the Commission's Office of Communications of informational presentations to community groups by the public utility scheduled after the filing of the transmission siting application so that the Commission, OCA and other interested parties can attend meetings or obtain copies of information being disseminated at the presentations.
This section cited in 52 Pa. Code § 69.3101 (relating to scope).