Section 69.2103 - Definitions
The following words and terms, when used in this section and § § 69.2101, 69.2102 and 69.2104 (relating to interconnection application fees), have the following meanings, unless the context clearly indicates otherwise:
Area network impact study-An engineering study conducted by an Electric Distribution Company of a local area network under § 75.40 (relating to Level 4 interconnection review).
Customer-generator-A nonutility owner or operator of a net metered distributed generation system as defined in § 75.1 (relating to definitions).
Facility study-A study conducted by an electric distribution company or a third party consultant for the customer-generator as defined in § 75.22 (relating to definitions).
Feasibility study-A preliminary evaluation of the system impact and cost of interconnecting the small generator facility to the electric distribution company's electric distribution system, as defined in § 75.22.
Level 1 review-The interconnection application review level in § 75.37 (relating to Level 1 interconnection review).
Level 2 review-The interconnection application review level in § 75.38 (relating to Level 2 interconnection review).
Level 3 review-The interconnection application review level in § 75.39 (relating to Level 3 interconnection review).
Level 4 review-The interconnection application review level in § 75.40 (relating to Level 4 interconnection review).
System impact study-An engineering study that evaluates the impact of the proposed interconnection on the safety and reliability of an electric distribution company's electric distribution system, as defined in § 75.22.
This section cited in 52 Pa. Code § 69.2101 (relating to statement of scope); and 52 Pa. Code § 69.2102 (relating to statement of purpose).