Pennsylvania Code
Title 52 - PUBLIC UTILITIES
Part I - Public Utility Commission
Subpart C - Fixed Service Utilities
Chapter 65 - WATER SERVICE
Subchapter B - LEAD SERVICE LINE REPLACEMENTS
Section 65.59 - LSLR program reports
Current through Register Vol. 54, No. 38, September 21, 2024
(a) An entity with an approved LSLR program shall file with the Commission a LSLR program report by March 1 of each year, in both print and electronic formats, including supporting spreadsheets. If an entity is implementing its LSLR plan as part of a Commission-approved LTIIP, the entity shall include a LSLR program report as part of the entity's AAO plan under § 121.6 (relating to AAO plan filings).
(b) An entity's LSLR program report must identify the preceding year's activities, including:
This section cited in 52 Pa. Code § 65.56 (relating to LSLR plan requirements).