Pennsylvania Code
Title 52 - PUBLIC UTILITIES
Part I - Public Utility Commission
Subpart C - Fixed Service Utilities
Chapter 65 - WATER SERVICE
Subchapter A - SERVICE GENERALLY
Section 65.22 - Customer advance financing, refunds and facilities on private property
Current through Register Vol. 54, No. 38, September 21, 2024
(a) If a customer advance is required from a bona fide service applicant for service from a company with gross annual receipts of $10 million or more and the bona fide applicant is unable to advance the entire amount due, the utility shall do one of the following:
(b) When a customer advance is required of a service applicant and an additional customer or customers attach service lines to the main extension within 10 years, the utility shall refund a portion of the advance to the customer in accordance with the utility's currently effective tariff. Deposits made for additional facilities other than the main extension, such as booster pumps, storage tanks and the like, are contributions in aid of construction and need not be refunded.
(c) A utility shall require a customer to pay, in advance, a reasonable charge for service lines and equipment installed on private property for the exclusive use of the customer.
The provisions of this §65.22 issued under the Public Utility Code, 66 Pa.C.S. § § 501, 504-506, 1301 and 1501.